Project GabE ECE 135 – Spring 2005 Week 9
Rahmin Sarabi Omar Al-Jadda Patrick Crosby Adam Durity
2
Gantt Chart
3
Progress Report Posted completed Midterm report to website
Tested two Tx’s Tested and verified functioning Rx
4
Tx Testing First test yielded non-working circuit
Laser driver not powered PROBLEM: ground pins from power supply not grounded on board SOLUTION: soldered a connection to ground plane FRONT BACK
5
Tx Testing Laser Driver now powered successfully
Signal trace performed to VCSEL INPUT OUTPUT from Laser Driver
6
Tx Testing We will set to meet modulation current requirements
MODSET potentiometer closes and opens eye We will set to meet modulation current requirements Tx output - high resistance Tx output - low resistance
7
Tx Testing VCSEL did not lase on both boards
Connected to pattern generator’s optical receiver Rx LOS indicator came on - VCSEL off Dr. Brooke’s approach to determine appropriate POT settings
8
Rx Testing Tested with input from pattern generator
Very good eye pattern
9
Upcoming Week Revise design and schematic for second board run
Address lasing failure Build second Rx Revise design and schematic for second board run Order second board