Execute Purchase Order South Shore Water Reclamation Facility Building 359 Odor Control System Repairs Commission Agenda Item #8.

Similar presentations


Presentation on theme: "Execute Purchase Order South Shore Water Reclamation Facility Building 359 Odor Control System Repairs Commission Agenda Item #8."— Presentation transcript:

1 Execute Purchase Order South Shore Water Reclamation Facility Building 359 Odor Control System Repairs Commission Agenda Item #8

2 Building 359-Sludge Dewatering Building
Primary Sludge from JIWRF and SSWRF: Sent to 3 receiving wet wells Thickened on 3 Gravity Belt Thickeners (GBTs) Thickened sludge then sent 6 storage tanks, then pumped to digesters

3 Bldg. 359

4 Wet Wells and Storage Tanks in Basement
GBTs on First Floor

5 Bldg. 359 Odor Control System
3 fiberglass vessels containing odor-adsorbing carbon media Ducts from wet wells and storage tanks to odor control vessels 5 blowers exhaust odorous air from wet wells and storage tanks, through carbon vessels to atmosphere

6 Bldg. 359 Odor Control System
Exhausted Treated Air Ducts from Bldg. 359 Fiberglass vessels Blowers

7 Bldg. 359 Odor Control System
31 years old Hasn’t operated for many years Infrequent odor complaints did not warrant repairing the equipment Renewed focus on reducing plant odors, staff recommends repairing system and operating again

8 Contract Scope Remove and dispose of spent carbon
Inspect odor control vessels to determine their condition Repair vessels as necessary Install new carbon

9 Project Bid VWM competitively bid the work
1 bidder: Butters Fetting Co. Within budget VWM will manage and oversee the work 90 day duration

10 QUESTIONS? No need in this case to re-state the request.