LINAC System Engineering / Design Status C.E. Rago
2
Design Elements Detailed design requirements
Engineering Specification Document (ESD) Documents to support fabrication & installation. Detailed drawings and models. Assembly procedures, component travelers, fabrication QA. Documents for long term operation & maintenance. System Schematics Project Data Base Design data and operational histories.
3
LCLS Installation and Commissioning Time-Line
X-Ray tunnel/FEH Install X-Rays in FEH LTU/Und/Dump FEE/NEH Install First Spont. Light CF Early Occupancy X-Ray Systems Checkout - Commission e- beam & Photon Systems Checkout CD-4b CD-4a S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M 2007 2008 2009 PPS PPS 2010 Photon Flux Measurements Controls checkout Re-commission Inj/BC2 to SL2 Operations LTU/Und/FEE Commissioning NEH Operations Linac/BC2 Commissioning linac/BC2 Install FEL Commissioning
4
Design and Fabrication Tracking Schedule
5
BC2/L3/BSY Status 2007 Installation
BC2 Status Designs are almost complete! Spot Shielding – drawings ready waiting RP final approval. Seismic proofing of center movable magnets is working. L3 Status Designs are complete! All beam line components/supports are in fabrication. Sufficient documentation for installation SOW. BSY Status Corrector & Quad Modification – with Accelerator Dept.
6
2007 Installation Status (cont.) BC2
7
2007 Installation Status (cont.) L3
8
BTH Status LTU Co-occupancy 2008
6/11 Section ID drawings released. Component Stands out for fabrication. Support Drawings for SOW / Stand Installation complete. Magnet Drawings Complete BYKIK Assembly Drift Tubes / Prototype & Standard Lengths complete. Working Repackaged diagnostics where necessary. Spot Shielding / Collimation
10
Electron Dumps Co-occupancy 2008
2/3 ESD pending RP analysis. 80% of design for fabrication complete. Working Main Electron Dump Electron Safety Dump ST1,2,3 (3 XES Stoppers d.s.Safety Dump) TDUND (Tune-Up Dump between LTU & UND) PCPM1 / Shielding (Collimator at Dump Vertex) Wall 1 Interface (Shield Wall d.s. of electrons)
13
Simplified Models / Project Data Base
Design / Data Base Sector 21 Simplified Models / Project Data Base Laser stopper BLM BC1 LX L1 Ins/SAB Wall
14
6-Months Look-ahead Complete Design2 for LTU & E-Dumps. Prepare Models for Operations. Secure all non-model information into DB. Support all Undulator & LUSI requests. Prepare to get small!
Similar presentations