Ward Park Restroom Timeline

Similar presentations


Presentation on theme: "Ward Park Restroom Timeline"— Presentation transcript:

1 Ward Park Restroom Timeline
December 2016: $15,000 General Improvement Fund (GIF) Grant Approved June 2017: $15,000 Additional GIF Approved July 2017: Bid Opening $62,800 Low Bid (Key Builders) August 2017: Contract Signed 120 Days to Complete the Project once a Notice to Proceed has been issued

2

3 Ward Park Restroom Timeline
September 2017: 9: $35,000 Additional GIF Approved 22: Pre-Construction Meeting Held at the Site City Contractor (Key Builders) Engineer (Schelle Architect) October 2017 3: Construction Started 120 Day Contract Estimated Completion Date: January 30, 2018

4 Ward Park Restroom Timeline
November 2017 $35,000 GIF Resinded

5 October 3, 2017 Construction Begins

6 October 4, 2017

7 October 5, 2017

8 October 10, 2017

9 October 20, 2017

10 October 20, 2017

11 October 20, 2017

12 October 31, 2017

13 October 31, 2017

14 October 31, 2017

15 October 31, 2017

16 November 11, 2017

17 November 11, 2017

18 November 11, 2017

19 November 11, 2017

20 November 11, 2017

21 November 27, 2017

22 November 27, 2017

23 November 27, 2017

24 November 27, 2017

25 November 27, 2017

26 November 30, 2017

27 November 30, 2017

28 November 30, 2017

29 December 7, 2017

30 December 7, 2017

31 December 7, 2017

32 December 7, 2017

33 December 7, 2017