Download presentation
Presentation is loading. Please wait.
1
Injector Physics C.Limborg-Deprey Feb.8th 2006
Layout Some Physics questions 110MV/m instead of 120 MV/m Residual Magnetic fields in GTL Commissioning plan
2
Injector Installation
Drive Laser May Laser Launch July Gun Region July Accel Region June Heater Region June Wall Region October Injection Region Aug-Nov 2006 Spect Region Aug-Nov 2006 Gun installation November 2006 Following Hot Test in Klystron Lab Waveguide through wall and up penetration October 2005 Injector Commissioning Start December 2006
3
Gun to Linac Region (GTL)
Spectrometer Courtesy J.Langton
4
GTL Design Normal incidence No second Valve in GTL
Low wakefield two symmetric mirrors <2% / for a x = 1mm No second Valve in GTL Wakefields computed, fine Diagnostics units finalized Gun Solenoid as close as possible to cathode Bucking Coil added cancels the 55 Gauss Bz field on cathode Compatibility with gun bake + cathode removal Mu-Shielding around ion pump under study Possible remnant quadrupole field issues from QG01, BXS handled PDR completed , FDR scheduled for February
5
From Accelerators to the wall region
L0b L0b L0a L0a Laser Heater Region Courtesy P. Stephens
6
From Accelerators to the wall
L0a moved downstream by 8 cm New tuning meets emittance requirement Second Solenoid length reduced to Leff = 20 cm higher Bfield for same focal length ok Suppressed one out of 2 BPMs in L0a-L0b drift 4 inch Phase monitor fits in Valve moved from L0a entrance to L0a-L0b drift Mu-shield metal wrapped at all possible locations Unfortunately not possible in GTL Laser Heater Real Estate Issue Space issue solved removed YAG04, moved QE02 Laser Heater Installed in summer 2007
7
DogLeg 1 (DL1) Spectrometer Beamline (SAB)
ē to linac DL bends Spectrometer bend
8
Wall region/ DL1 / SAB Conclusion DL1 SAB
No space issues SAB YAGS1 (for alignment laser) BXS accommodate 4 ports (X-Chamber) Alignment laser line Wire-Scanner Photo-multiplier port OTRS1 depth-of-field issue solved (for slice energy spread) Non-standard layout (see Diagnostics) Radiation Shielding issue of cameras still pending BPMS3 moved to high dispersion region (resolves = ) Conclusion Engineers can accommodate all required components All Physics specs. finalized at this point, (no more modifications accepted)
9
If only 110MV/m available instead of 120MV/m? 1nC tuning
fwhm [ps] r [mm] rf [] Bsol [kG] 80 [m.rad] proj [m.rad] z 110MV/m 10 ps 1.1 29.3 2.3385 0.95 1.05 0.968 10ps 1.2 28.3 1.0 1.12 0.935 12ps 30.3 2.3371 0.92 1.02 1.080 14ps 0.9 2.3308 0.88 0.97 1.157 120MV/m (Nominal) 32.3 2.5198 0.91 0.98 0.948
10
If only 110MV/m available instead of 120MV/m? 0.2nC tuning
fwhm [ps] r [mm] rf [] Bsol [kG] 80 [m.rad] proj [m.rad] z 110MV/m 6.5ps 0.4 31.3 2.346 0.37 0.44 0.704 0.5 32.3 2.343 0.405 0.660 120MV/m (Nominal) 2.536 0.35 0.445 0.657 NB: those tunings assume a thermal = 0.6 mm-mrad per mm (whereas the start-to-end simulations assumed a very conservative number of 1.2 mm-mrad per mm)
11
Residual Magnetic fields in GTL
Undesired quadrupole fields along GTL damage emittance compensation Quadrupole components in solenoids Remnant quadrupole fields in QG01 and BXG Solenoid QG01 QG01 BXG BXG Solenoid 2 Gun L0a Specifications Integrated quad. S1 QG01 BXG S2 B/x * Leff [G] 2 3 6
12
Residual Magnetic fields in GTL
Int. Quad. 2.7 G Example SOL1 : 5% growth in / with 2.7 Gauss Mitigation Solenoid 1: shimming after magnetic measurement QG01 : degaussing of magnet (procedure already established ) BXG : careful design Solenoid 2: shimming after magnetic measurement
13
Injector Commissioning
Discussed every 5th week with LCLS physicists/operators group Incorporated into large MS Project document for links Discussed weekly inside Injector group (Bong, Dowell, Limborg, Loos, Schmerge …) Based on 2 shifts per day Resource loading still to be refined 2 physicists per shift + 1 control person + 1 operator guests List of high level applications Schedule Outline Starts with RF Gun cold test (May 06) and hot test (summer 06) First beam at 135MeV dump ( Dec.06) 7 months of characterization and optimization (through BC1)
14
December 06 December 06 Schedule 2006 2007
15
High Level Applications
Cathode characterization (QE, uniformity, Thermal emittance) Steering in L0a Longitudinal phase space measurements at BXG Bunch length measurement with transverse RF deflector(s) Emittance meas. (multi-wire, multi-OTR, quad-scan, slice) Power-steering through beamlines, with corrector weights Difference orbit fitting, including internal kick Longitudinal phase space measurement at BXS Tomography (Longitudinal and Transverse) …
16
Example of procedure (1): Steering in L0a
Solenoid mispositioning 250 m, 250 rad Earth Magnetic field 2mrad/m vert. No space for mu-metal shielding in GTL By ~ 0.35 G Bx ~ 0.12 G Offset as large as 4mm, 4 mrad, without steering Solenoid SC0 SC1 SC2 Gun BPM2 BPM3 L0a BPM5
17
Example of procedure (1): Steering in L0a
L0a solenoid off Orthogonal knobs at SC0 BPM2, BPM3,BPM5 SC0 and SC1 adjusted to steer in L0a to better than 100m 120 rad Scaling of SC0 orthogonal knobs with solenoid implemented in software Solenoid SC0 SC1 SC2 Gun BPM2 BPM3 L0a BPM5
18
Example of procedure (2): Longitudinal Phase space measurements
Direct Longitudinal Phase Space measurement Transverse deflecting cavity y / time correlation (with V < 0.5MV/m, 0.5mrad over 10ps ) Spectrometer x / energy correlation Longitudinal Phase Space at TCAV Spectrometer Screen
19
resolution < 5keV 5keV -> 40 keV will be easily measurable
20
Conclusions Physics Requirements have been finalized
Iteration (Physics/ Mechanical Designer) works well Converged for GTL, L0a-L0b drift, Matching Section Nearly finalized for SAB, Laser Heater region Physics issues identified Importance of Earth magnetic field Control of residual quadrupole fields Commissioning schedule under completion Applications to be written
21
BACK-UP
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.