Proposer: Steve Mulinganie, Gazprom Energy Panel Date: 20th June 2019

Similar presentations


Presentation on theme: "Proposer: Steve Mulinganie, Gazprom Energy Panel Date: 20th June 2019"— Presentation transcript:

1 Proposer: Steve Mulinganie, Gazprom Energy Panel Date: 20th June 2019
UNC 0696: Addressing inequities between Capacity booking under the UNC and arrangements set out in relevant NExAs Purpose of Modification: To the extent to which a Consumer has entered into a bi-lateral Network Exit Agreement (NExA) with the relevant Transporter then any new or additional capacity charging should only apply from the relevant date set out in the NExA. Proposer: Steve Mulinganie, Gazprom Energy Panel Date: 20th June 2019

2 Why change? In circumstances were separate (NExA) and UNC arrangements exist we have identified a conflict leading to a detrimental impact on Customers The NExA is between the Transporter & the Customer The UNC is between the Transporter & the Shipper The only party who is aware of the details of both the NExA and the UNC is the relevant Transporter If the NExA sets out a date from which Capacity can be off-taken and prohibits the customers taking capacity prior to this date we believe it is unreasonable to expect the Customer to pay for that Capacity prior to that date

3 Options Change the arrangements to align charges for capacity being off-taken under the UNC with the relevant date in the NExA

4 Solution It is proposed that any new or additional capacity requested under the UNC should only be chargeable from the date set out in the NExA. Business Rule 1 Any requests for new or additional capacity shall, were a relevant NEXA exists, only be chargeable from the relevant date set out in the NEXA. Business Rule 2 This change would be effective from [1st September 2018].

5 Recommended Steps The Proposer recommends that this modification should be: Not subject to self-governance because the change is material in relation to those customers it impacts Workgroup assessment to develop the modification for [3] months Preference would be for Distribution workstream to discuss