The Form of Procurement for the EcoHome Project
A excerpt from the EcoHome project´s Design Brief:
2
PRIME (MAIN) CONTRACTS
THE DEVELOPER OF THE ECOHOME PROJECT WANTS 100% INFLUENCE ON THE DESIGN FORM OF PROCUREMENT: TRADITIONAL TRADE CONTRACTS OR PRIME (MAIN) CONTRACTS Project tender on basis of Client´s architect´s 100% detailed project: Contractor has no influence on design PROGRAMMING (THE BRIEF/TOR) SCHEMATIC DESIGN DESIGN DEVELOPMENT DETAIL DESIGN : DRAWINGS/TENDER DOCS. BIDDING PHASE CONSTRUCTION PHASE OPERATION &MAINTENANCE PHSE
3
PRIME (MAIN) CONTRACTS
Invitation to tender for either a main contractor, or individual trade contract TRADITIONAL TRADE CONTRACTS OR PRIME (MAIN) CONTRACTS DETAIL DESIGN : DRAWINGS/TENDER DOCS. Invitation to tender to each individual contractor Invitation to tender to Main Contractor only!