Project Overall Status – July 8 to 19, 2019

Similar presentations


Presentation on theme: "Project Overall Status – July 8 to 19, 2019"— Presentation transcript:

1 Project Overall Status – July 8 to 19, 2019
Program is on track, per timeline, scope and budget Security Mapping activities impacting completion of UAT Current DG2 Schedule has no “float” remaining in timeline Scope Requirements Traceability Matrix (RTM) needs to be updated to validate original RFP requirements have been implemented, tested, and end users trained on the processes and functionality Schedule Monitoring scope and timing of: Budgeting Tool, Continuing Education, Online Admissions Application, Physical Assets and OBIA implementations Budget G Currently tracking under budget New Technology Budget required by OFM/OCIO has been submitted and approved Allotment for Gate 4 funding has been submitted Executive Summary The project is tracking per schedule and under budget. Scope review and definition for each deployment continues due to rework of key solutions. Each Deployment Group (DG) is engaged and all colleges now have an Initiation or Implementation Work Plan: DG2 is in the Transition Phase. Colleges and SBCTC are engaged in User Acceptance Testing sprints. ctcLink will be offline for the DG2 upgrade Oct and again for cutover activities Oct   DG3 is in the Construct Phase, focused on Conversion and Data Validation. DG3 Testing/Training road shows are underway. DG4 is in the Initiation Phase, with all colleges past the halfway mark on deliverables. Gate 1 Initiation Phase Peer Review will be July at Highline College. DG5 colleges are in the Initiation Phase and have begun Initiation Deliverables public status reporting. PMO team visited colleges in June for Initiation road show. DG6 is in the Initiation Phase and will start public status reporting this fall. The Initiation Phase Road Show will be in Oct Planning meetings have begun with technical colleges to capture differences between technical and community college business practices. The new Chart of Accounts was implemented in July for Spokane and Tacoma. Final contract negotiations continue for a new Continuing Education solution. An RFI is being developed for the Online Admissions Application (OAA), in parallel with additional improvements to the current OAA solution. The Budget Planning Tool work group is working on finalizing business and technical requirements. Many college PMs will participate in the Prosci 3-day training in August in Centralia and Wenatchee to learn organizational change management principles. Overall Status Summary per Deployment Group DG# PMO- Reported Status Comments College/ Agency Self-Reported Status DG2 Y Security Production Mapping is in progress and production security must be tested to complete UAT Clark G SBCTC Spokane R Tacoma DG3 College Configuration in progress Conversion cycles have begun Cascadia LCC Olympic Peninsula Pierce DG4 College teams working on Initiation Phase activities Implementation begins Nov. 2019 DG5 Implementation begins March 2020 DG6 Implementation begins Nov 2020 1

2 Top Risks Reported – as of July 19, 2019
LEGEND: Critical High Moderate Low C H L M Risk Level Risk Description Mitigating Actions Submitted by (name, org/college), Deployment Group & Date Risk Owner (s) H Chart of Accounts (CoA): User adoption and successful deployment (scheduled for July 1, 2019) is critical for Deployment Group 2 (DG2) timeline. Update: Phase 1 cutover activities completed. Phase 2 and sub-ledger closing activities are in progress and were completed on July 10.  Final configuration (Phase 3)  completed the week of July 15.  College SMEs  and Emmett are continuing to work through and troubleshoot issues Emmett Folk, ctcLink PM for FIN & HCM Team DG2 Impacted, Risk Date:10/12/2018 *also Risk submitted by Matt Connelly, Spokane District PM on 10/23/2018 Emmett Folk Clark: Student Financials – Clark submitted three risks. Update: Items related to Student Financials, Financial Aid, General Ledger and coordination between Student Financials and Finance. These items have been discussed with Clark. Cycle 4B is planned to mitigate these risks. A follow-up will be scheduled with Clark’s PM after Cycle 4B. Cycle 4B is scheduled for July 12, Colleges will validate by 8/9. Susan Maxwell, Clark College PM DG2 Impacted, Risk Date: 2/1/2019 Risks #50, #51, #52 John Henry Whatley, Emmett Folk, Chandan Goel ctcLink Team: The GL & SF Conversion logic/ requirements for the Go Live term has still not finalized. If not addressed soon, it creates a risk of not being made available for colleges validation and meeting the timeline for Cycle 4B.  Update: Finance team met with Student Financials team to discuss AR (Accounts Receivable) items and alignment in data conversion activities. Additional discussion are needed to further define the process. John Henry Whatley DG2 Impacted, Risk Date: 7/8/2019 Risk #71 John Henry Whatley, Christyanna Dawson Top Issues Reported – as of July 19, 2019 LEGEND: High Moderate Low H M L Issue Level Issue Description Status Update Submitted by (name, org/college), Deployment Group & Date Issue Owner (s) H Security Mapping activities to mitigate UAT timeline, have not addressed the new Security Design Production user access. Update: The ctcLink team is highly concerned about the Production Security Mapping for DG2 Colleges and entering new Security into one of the UAT cycles.  Although there are no other options due to the schedule, this will be a challenge for the DG Colleges and SBCTC as well as potential impact to the remaining UAT cycles.  ctcLink PMO submitted for ctcLink CS, HCM, FIN Team DG2 Impacted, Issue Date: 4/16/2019 Tara Keen, Security Team M Clark – Accessibility Items Clark has submitted issues around accessibility items they have identified. We are tracking these items and will provide this information to the vendors to review and test when they are onboard (estimated for August). Susan Maxwell, Clark College PM DG2 Impacted, Issue Dates: 6/27/2019 Issues: #39-48 Owners TBD 2

3 ctcLink Quality Assurance Scorecard / Moran Technology Consulting Report June 2019
Overall Status Y ctcLink Quality Assurance Scorecard - Moran Technology Consulting , November 2018 STATUS PROJECT AREA DESCRIPTION / NOTES G SBCTC/Governance Go-No Go Decision for FLC implementation of new Chart of Accounts was made by Steering Committee. The ctcLink Executive Leadership Committee will have a change to voting members with the new WACTC-Tech appointed college presidents. Project Management Project Management Office (PMO) is fully staffed, working well together and continuing to address improvements in project management processes. PMO has hired a PM to manage Schedules (individual starts in July). Y Phase Scope QA remains concerned about the number of solutions to be re-implemented to replace/augment current PS functionality. Based on the May status of replacement solutions, it does not seem possible that these will be decided upon and readied for DG2 scope inclusion. Schedule Status DG2/DG3/DG4 schedule overlap and resource constraints directly impact all deployment groups. Schedule compression and key project resources are heavily allocated to multiple DG2 workstreams and supporting DG3 tasks. DG2 schedule is dependent on CoA implementation at CCS and TCC colleges. Priority must continue to be focused on DG2 project and college readiness. QA recognizes that the high level of DG2 related activities leading up to Go-live will be stressful to the ctcLink project staff. QA is also concerned that the ctcLink Project staff and ERP support team will be stressed for a number of months once DG2 is live, with anticipation of a higher volume of new support tickets. Training Development of Training materials to support remaining Sprints was underway in June. Training team and consultants are working on preparing materials for Sprints 4/5/6. QA continues to be concerned that considerable development work still remains for the courses to support end-user training. Testing DG2 UAT Sprints, were underway in June. Good sprint participation by the DG2 colleges. UAT has identified configuration and process errors that have been resolved. Consultant contracted to fill Testing Manager role was delayed on-site and (expected to start in July). The DG2 Testing workstream remains a major QA concern since it requires continued active DG2 end-user participation. QA is also concerned about the execution of dual parallel testing for payroll, financial-aid, and tuition calculation. Configurations / Data Conversion Technical work for beginning CoA implementation started in June once Go-live decision was made by Governance. This work required the ctcLink Project team working closely with the ERP support team. CoA implementation Steps 1 and 2 were completed as scheduled. Conversion and Production implementation of the Bio-Demo data for Clark College and SBCTC is scheduled for July. DG2 Go-live production cutover planning sessions began in June. Organizational Change Management PMO/OCM is actively engaged with all colleges now involved with their DGs.QA is concerned that PMO remains focused on the DG2 schedule/priority activities. The project is aware that effective communications and messaging is important to success of the project. QA supports the efforts the project is undertaking to prevent false messages from being sent. Project Staffing Project staffing is adequate at this time and continues to make staffing adjustments as appropriate. PMO is recruiting for open positions. PMO to begin using off-shore technical resources to perform and augment systems integration testing work. Technical Environment The IT division continues addressing processes and critical staffing. The ERP Change Management Board is being re-implemented to improve coordination and scheduling of changes. IT is reviewing staffing models at other PeopleSoft ERP community college systems for staff and budget sizing. The development/implementation of security roles for the colleges has now become a critical issue and is being addressed by the ctcLink PMO. Service Level Agreement has been distributed to colleges. LEGEND GREEN YELLOW RED Risk Description: Low risks may be encountered. NO immediate action needed Moderate risks may be encountered. Serious deficiency and action item recommended. High risks may be encountered. Needs to be escalated and can impact project effort or cost. 3

4 WA State Office of the Chief Information Officer (OCIO) Oversight
WA State Office of the Chief Information Officer (OCIO) Oversight as of July 2019 Overall Status Y WA State Office of the Chief Information Officer (OCIO) Oversight WA State Office of the Chief Information Officer (OCIO) Oversight OCIO Conditions to new ctcLink Investment Plan Approval Status G 1 Project must remain in line with SBCTC and OCIO policies Ongoing 2 QA (Moran) to report to ctcLink executive sponsor and State CIO Complete 3 Follow pre-determined OFM funding gates and approvals 4 Monthly status reporting 5 Continue reporting on Remediation items in Integrated Work Plan Y 6 OCIO approval of the 4 remediation solutions: Budgeting tool, Continuing Education Application, Online Admissions Application In Progress 7 OCIO must be notified prior to use of contingency funds N/A 8 Perform a post-implementation review (lessons learned) after each deployment and post on the OCIO dashboard within 30 days of go-live Planned as Activities in Project Work Plans 9 Process and timeline for filling the SBCTC CIO position by 1/31/2018 ctcLink Technology Pool Status and Gate # Status G -- Pre-IT Pool Implementation, Stability & Remediation Approved 1 Planning & Remediation 1/1/2018 2 DG2 – Initiation & Structure Phase 3 DG2 – Construct Phase DG3 – Initiation & Structure Phase 1/1/2019 4 DG2 – Transition & Deploy Phase DG3 – Construct Phase DG4 – Initiation & Structure Phase Pending Approval 7/1/2019 5 DG3 – Transition & Deploy Phase DG4 – Construct Phase DG5 – Initiation & Structure Phase Future 2/2020 6 DG4 – Transition & Deploy Phase DG5 – Construct Phase DG6 – Initiation & Structure Phase 10/2020 7 DG5 – Transition & Deploy Phase DG6 – Construct Phase 2/2021 8 DG6 – Transition & Deploy Phase 10/2021 9 Contingency Deployment N/A 2/2022 Note: New ctcLink Investment Plan approved by OCIO, with above conditions, on Jan. 19, 2018.

5 Budget Status – as of June 30, 2019

6 Human Capital Management
Pillar Status – July 8 to 19, 2019 Campus Solutions G Accomplished this period Clark Dual Processing SIT end to end (100% complete) Provide scheduling parameters to Legacy team for DG2 Cycle 4b Hand-Off DG3 Cycle 3 College Optional Files to Legacy Team Continue reviewing requirements for Guided Pathways system configuration FAST Work Group meeting (SAP work) Review DG2 Cycle 4b crosswalks Clark Transfer Credit Rule Go Live Workshop Prep Review DG3 assignment submissions for configuration DG2 Sprint 3 CS UAT Continue DG3 FIT Continue DG2 SIT Continue UAT material planning/build Planned for next period Hold Clark Transfer Credit Rule Go Live Workshop Continue to review requirements for Guided Pathways system configuration Validate DG2 Cycle 4b conversion Support Security Redesign activities Support UAT for DG2 Colleges FA Parallel Testing – Dual Processing Prep for Parallel Testing – Tuition Calculation Plan for EMPL ID conversion to PRD Human Capital Management Y Accomplished this period Collected DG3 Cycle 3 Data Files Continued DG3 Cycle 3 Prep Activities Continued review of Security Redesign Role/Permission List Definitions Continued Payroll Parallel Testing Activities Continued UAT support activities Continued DG2 UAT diagram/scenario updates Continued DG2 UAT supporting content build Continued review of DG2 Training content structure and materials Continued DG2 and DG3 configuration build-out in FNC environment Planned for next period Begin DG4 BPFG session planning Continue DG3 Cycle 3 Prep Activities Continue review of Security Redesign Role/Permission List Definitions Continue Payroll Parallel Testing Activities Continue UAT support activities Continue DG2 UAT diagram/scenario updates Continue DG2 UAT supporting content build Continue review of DG2 Training content structure and materials Continue DG2 and DG3 configuration build out in FNC environment *If status is yellow or red, describe why. DG2 UAT and pre-UAT training supporting materials are being provided on a just in time basis. The concurrent DG2 and DG3 activities are causing the team to prioritize externally-/client-facing activities and deadlines/starts for certain internal tasks continue to get missed. Financial Services Y Accomplished this period Collected DG3 Cycle 3 Data Files Continued DG3 Cycle 3 Prep Activities Continued review of Security Redesign Role/Permission List Definitions Continued DG2 UAT support activities Continued DG2 SIT Test Execution Continued DG2 UAT supporting content build Continued review of DG2 Training content structure and materials Continued DG2 and DG3 configuration build-out in FNC environment Planned for next period Begin DG4 BPFG session planning Continue DG3 Cycle 3 Prep Activities Continue review of Security Redesign Role/Permission List Definitions Continue DG2 UAT support activities Continue DG2 SIT Test Execution Continue DG2 UAT supporting content build Continue review of DG2 Training content structure and materials Continue DG2 and DG3 configuration build-out in FNC environment *If status is yellow or red, describe why. DG2 UAT and pre-UAT training supporting materials are being provided on a just in time basis. The concurrent DG2 and DG3 activities are causing the team to prioritize externally-/client-facing activities and deadlines/starts for certain internal tasks continue to get missed. Pillar Status – as of 6/8/2018

7 Workstream Status – July 8 to 19, 2019
Communications G Accomplished this period cELC committee transitional planning and communications Continued planning for Executive Sponsor Seminar on 7/30 Communications by Phase/Countdown meeting planning with DG3 PMs and Comms staff DG2 Go/No-Go decision package timeline options Accessibility update blog re vendor process, testing, prioritization Steering Committee meeting materials developed, distributed Planned for next period Support July 30 Exec Sponsor Seminar Hold Comms by Phase Planning meeting on July 31 Accessibility blog post, phase 2 Continue Comms Advisory Committee planning Communications Office scope/activities Templates work (including Critical Communications Template) Technical G CONVERSION Accomplished this period DG2: Conversion Issues review/resolution. DG2: Establish the timeline for Cycle 4B. DG2: Successfully migrated objects to Conversion Environment (CTS). DG2: Successfully moved all tested configurations to date into the CTS. Planned for next period DG2: Conversion Issues resolution. – In Progress DG2: SF Parallel Test activities. DG3: Cycle 3 Conversion Activities. DEVELOPMENT Support and work on Service Desk, FIT, SIT & UAT tickets for CS, HCM & FS pillars. Migrated the retrofit project (for HCM PUM 31) to HCDEV & HCTST environments. Remediation development for HCM for CEMLI R-266. Unit Test completed for OAA Application Fee waiver code Unit Testing Nelnet Retrofit ENVIRONMENTS Coordinated PUM Image Update in Project environments. Coordinated Load Testing Project work. DG2 cycle4b environment refresh. Fluid Migration strategy. Prepare STAT trainings for Functional Team. STAT trainings DG3 cycle 3 and DG3 Cycle4B environment support. Testing Y Accomplished this period Continued system integration testing (SIT): Finance 100% complete, HCM over 80% complete, CS 60% complete Completed Sprint 4 UAT Provided metrics on SIT and UAT status Continued to build UAT materials for final sprints Supported Sprint Closure for 1-3, UAT 4 execution Began Parallel Testing: Payroll nearing completion, Financial Aid Dual Processing began, Student Financials preparing to start next week Planned for next period Prepare for UAT Sprint 5 and 6 execution Continue to build UAT materials, System Integration Testing, UAT support, UAT/SIT metrics Continuation of Load Testing Reviewing PUM Image releases for regression testing in Sprint 6 *If status is yellow or red, describe why. Overlapping project tasks that utilize the same resources may impact testing. Organizational Change Management G Accomplished this period Meet with DG2 PM’s to discuss how change management activities are going with their teams Continued planning DG4 Peer Review Started meeting with DG3 colleges about testing, training, and life after go-live. Conducted onboarding with new college PMs Continued planning DG6 Road Show around Initiation Deliverables in October Planned for next period Continue to work with CPW Facilitators and Functional Teams to determine scope for upcoming sessions Continue College Relations/OCM Check-ins with DG3, DG4, DG5 and DG6 Continue development on schedule of events with PMO and all Deployment Groups Training Y Accomplished this period Currently at 75% for Sprint 5 and 25% for sprint 6 Started working in all pillars on development of End User Training Courses At 25% for all End User Training Canvas Courses Worked with vendor on HCM UAT training deliverables Continued work to define training scope, work assignments, activity durations, and dependencies Planned for next period Continue to work on Pre-UAT Training materials Continue to work on End User Training courses *If status is yellow or red, describe why. Large amount of materials needed with upcoming timelines

8 Deployment Group 2 Timeline (High Level Phases)

9 Deployment Group 2 Self-Reported Status – July 8 to 19, 2019
Clark College G Accomplished this period Began Sprint 4 of UAT Payroll Parallel testing underway Final review of Courses in production Assessing training schedule to plan for locations. Mondays have up to four sessions simultaneously. Dates and deadlines related to Go-Live sent to campus Planned for next period Query 101 training July 25 Host project team 7/29-8/1 for transfer course equivalencies Finalize Go Ready checklist Finalize student communications and graphics Planned, but not completed More progress on AARs and documentation – ongoing slowly Community Colleges of Spokane R Accomplished this period Continue to work through post CoA issues/cleanup Security Role meetings to complete mapping guide template for CCS to begin validating new security roles. Matt C working with SBCTC on best way to map Old to New. FY Close –DG2 UATs – Wrapped up Sprint 4. Sprint 5 starts 7/29 Finance team delivered new CoA Projects spreadsheets required to SBCTC Planned for next period Chart of Accounts Redesign: Work in progress on CoA manual conversion work required post CoA rollout EOY/EOM: Complete tasks prior to YE July 24 close date. Finalize Closing of FY16, 17, 18. Security Issues: CCS to complete validating roles assigned to non-sensitive data vs sensitive data. SBCTC preparing to remove all old query roles. Security Role Redesign: Pending new Security Role spreadsheets from SBCTC so we can start validation exercise. *If status is yellow or red, describe why. FY Close activities for 16, 17, 18 & 19 at risk. CCS Chart of Accounts – Continue to work through blocking issues in Finance. SBCTC addressing issues but CCS continues to be impacted by new blocking issues as of 7/23. Coming up to Year End 7/24 Close date. Security Role Redesign – CCS still waiting for SBCTC to provide us any spreadsheets with the new security roles, so we can begin validating and assigning correct security roles. SBCTC was not able to provide us the Role Mapping Guidance spreadsheet as originally communicated. Scope of work has grown substantially for both post-CoA cutover and Security Role mapping/validation. SBCTC Agency Y Accomplished this period WAPAY now in production! 7/17. Celebration held 7/18 Travel & Expense Open Houses completed 7/10 and 7/17. Approximately 80 attendees between three June and July sessions! Change Readiness Survey #3 sent to agency all-staff by Executive Sponsor John Boesenberg. 7/17 Planned for next period HR Leave and Self-Service ctcLink Open House Demo Only 7/29 UAT Sprint 5 – “End-to-end” regression testing 7/29-8/6 Planned, but not completed Status is needed regarding completing a list of all supplemental systems. *If status is yellow or red, describe why. FIN and HR are on track. Payroll is making great progress in UAT Sprint 3. Open Houses are giving all-staff opportunities to see and “touch” the ctcLink system for Travel & Expenses with plans underway for HR Self-Service. However, manageable issues remain in completing Payroll testing, including UAT Sprint 3. Issues remain regarding security and approval work flow engine (AWE). Tacoma Community College G Accomplished this period Local SMEs attended ctcLink Security redesign group, ctcLink PM groups, ctcLink governance groups, various ctcLink status meetings Participated in ctcLink Security redesign activities Participated Chart of Accounts meetings and activities Participate in UAT, monitor and communicate UAT status Received Training info from SBCTC Started coordinating Training Planned for next period Local SMEs attend ctcLink Security redesign group, ctcLink PM groups, ctcLink governance groups, various ctcLink status meetings Chart of Accounts meetings & work activities Participate in UAT Work with SMEs, Pillar Leads, TCC Leadership to get better participation in the project Plan and execute OCM for DG2 project Monitor UAT status

10 Deployment Group 3 Timeline (High Level Phases)

11 Deployment Group 3 Self-Reported Status – July 8 to 19, 2019
Cascadia College G Accomplished this period Completed all data validation requirements for cycle #2 CS pillar completed final optional assignments (due 6/28/19) Finance completed all cycle #3 homework assignments due 7/17/19 Payroll attended VC12b CPW, July 17-19 CS and FIN completed data cross-walk activities Planned for next period Internal Training Management planning Internal Testing Management planning Preparing for Reporting & Query Management Plan Pierce College District G Accomplished this period SMEs completed/submitted Cycle 3 conversion files. College Leadership, Implementation Team and SMEs participated in six-month follow-up session with SBCTC project team. SMEs participated in follow-up WebEx sessions regarding Cycle 3 conversion. HCM SMEs participated in Time & Labor Administrative Tasks CPW. Planned for next period Schedule/plan follow-up meeting with College Leadership, Implementation Team and SMEs – planning next 6 months. Identify Training Lead Participate in upcoming Common Process Workshops Planned, but not completed Review applicants for project positions. Review and update Communications Plan Review and update internal Training Plan with college Training Team. Identify/establish training space. Lower Columbia College G Accomplished this period Completed all data validation requirements for cycle #2. SME’s completed/submitted Cycle 3 conversion files. College leadership, Alignment Team and SME’s participated in the follow up session with SBCTC project team at LCC. CS and FIN completed data cross-walk activities. Onboarding activities completed for new project manager. Planned for next period Reporting lead and SME’s will attend query development workshop at Clark College. Continue on campus messaging and communication about ctcLink. Continue to develop forecasting tools to track staff workload and project hours. Identify UAT/Training Space Peninsula College G Accomplished this period HCM Completed FWL assignments SME’s continue to meet with project to fix errors Attended Time & Labor CPW Planned for next period Preparing next round of Validation, bringing on more SME’s Olympic College G Accomplished this period Continued work on ATD/ctcLink Teams for Residency, Choosing Academic Plan, Changing Academic Plan Completed cycle 2 validation lessons learned Re-started Change Impact Analysis planning Planned for next period Restart Change Impact Analysis Workshops Planned, but not completed Additional CIA Workshops

12 Deployment Group 4 Dashboard Reports – July 8 to 19, 2019
DG4 Initiation Phase Completion Summary Percentage of deliverables completed and tracked in Project Web App (PWA) by each college: College Orientation & Resourcing College Project Planning (from templates) Conduct Initial Data Cleansing Document Current Legacy Business Processes Supplemental Systems Analysis DG4 target percentages will be added in August 2019. College/District As of July 19, 2019 Centralia College 65% Edmonds Community College 60% Highline College 63% Seattle Colleges (3) 57% Wenatchee Valley College 68% DG4 Pre-Implementation and General Timeline G

13 Deployment Group 5 Dashboard Reports – July 8 to 19, 2019
DG5 Initiation Phase Completion Summary Percentage of deliverables completed and tracked in Project Web App (PWA) by each college: College Orientation & Resourcing College Project Planning (from templates) Conduct Initial Data Cleansing Document Current Legacy Business Processes Supplemental Systems Analysis College/District As of July 19, 2019 Target Percentage for July 2019 * Bellevue College 10% 35% Bellingham Technical College 24% Big Bend Community College 22% Everett Community College Grays Harbor College 30% Green River College 31% Skagit Valley College 18% Whatcom Community College DG5 Pre-Implementation and General Timeline G

14 ctcLink Remediation Status Reports – July 8 to 19, 2019
Solution Status Due Date Campus Solutions 10 of 45 remain open DG3 Financial Management 5 of 39 remain open DG2 Human Capital Management 6 of 25 remain open Faculty Workload Complete March 2019 DRS Redistribution May 2019 Absence Management April 2019 Security Audit Controls Security Redesign / Mapping FLC / DG2 Student Billing/Third-Party Billing Budget Planning Work Group Finalize Requirements Jan 2020 Online Admissions App RFI Being Developed Continuing Education Contract Finalization Chart of Accounts (revised) Due/Finish Status Tacoma CC Chart of Accounts Adoption Kickoff Dec. 12, 2018 Complete CCs of Spokane Chart of Accounts Adoption Kickoff Feb. 1, 2019 Foundational Chartfield Configuration March 22, 2019 College Configuration Review and Updates May 3, 2019 Functional and System Integration Testing May 10, 2019 User Acceptance Testing May 10 - June 3, 2019 May 28 – June 14, 2019 College Readiness Gate / Go-No Go Discussions June 12-14, 2019 Readiness Gate / Go-No Go Decision June 18, 2019 Community Colleges of Spokane R Progress made on overall remediation conditions over the past five months, but remains Red with FY 16, 17, 18 Close and delay of Security Role Redesign rollout. Delay of new Security Roles mapping availability and the overlap of projects (post CoA manual work and blocking issues, EOY tasks, DG2 UAT Training/Testing, FY Closing of 16, 17, & 18) are all impacting college staff and normal operations now through October 2019. Security Role Redesign: Scope for validating security role mapping validation exercise has now grown substantially as SBCTC was not able to provide us the mapping helper guides as initially communicated. As of 7/23, we have not received any Security Role spreadsheets to even began validation. Chart of Accounts: CoA conversion also resulted in substantial manual work; some planned and some unplanned work. SBCTC providing money for resources to assist, but that impacts existing resource time as well. Tacoma Community College G Remediation Items progress this period See SBCTC status update for Remediation items, tickets, and worklist. Accomplished this period Participate in Budget Tool planning. Monitored remediation items progress and communicate to local stakeholders

15 Other ctcLink Project Activities – Status as of July 19, 2019
Solution Status RFP Publish Solution Decision Accessibility Develop and published RFP Work Group engaged to evaluate RFP Responses Final Decision on Vendors to be awarded Vendor contracts awarded SOW for Accessibility Testing underway 5/10/2019 Testing Prior to DG2 (October 2019) Continuing Education RFP was developed and approved by Governance RFP proposals were due November 15, 2018 3 Vendors responded and subgroup is evaluating solution Governance approved procurement and decision of Vendor Vendor contract being finalized for scope and cost 10/15/2018 Contract Draft Complete Overall Pricing in Negotiations Online Admissions Application Sub-Committee finalized OAA requirements Project Team performed Fit/Gap of ctcLink functionality OAA workgroup evaluated select solutions currently in use at other PeopleSoft universities and colleges OAA workgroup developing a short list of best/possible solutions to identify those solutions on 2/12/2019 RFI to understand possible solutions and costs before final decision on RFP or custom solution Continue to enhance current OAA based on requirements for RFI TBD RFI requested Current ctcLink OAA requirements being prioritized prior to continue improvements Budget Planning Tool Committee formed to review, finalize, approve Budgeting requirements Budget Planning Tool Work Group meetings underway to finalize requirements and vet Oracle PBCS Solution If needed, develop RFP Work Group Kick Off Members reviewing Original RFP Budget Requirements Physical Inventory (Asset Tracking) Vendor Solutions being evaluated New PS Functionality will provide integration for asset tracking scanners directly with ctcLink and is ready for DG2 5/21/2018 DG2