1 MRV system budget and scheduling Short overview installation
Dr. Marcelo juni Ferreira ESS Vacuum Section Leader European Spallation Source ERIC 28/05/2019

2 Outline Background of ESS monolith solution,
Introduction to ESS Vacuum System, Vacuum Standardization Vacuum requirements: TARGET Monolith Rough Vacuum System specifications and interfaces,

3 ESS Monolith Vacuum System
Brief history: cost/budged April/2014 Cost/budged was planned as He solution only (pump/purge). Jun/2017 Service Level Agreement Vac-TARGET Div. for the Monolith Vacuum system solution Feb/2019 Formal responsibility transfer of the Monolith Rough Vacuum System to the ESS Vacuum Section on the original cost/budged from He solution (≈ 1.1 M€ no-labor only), May/2019 Monolith Rough Vacuum CDR (alignment of scope for Vacuum Section responsibilities)

4 Original Vacuum solution budged
Item Value [k€] Monolith rough vacuum, 2 bar gauge pressure operation General activities and tasks related to vacuum systems for target including travel 165.4 k€ Design and fabrication support both at ESS and partner facilities (labor) 133.8 k€ Eng: 1.2 FTE Designer: 0.5 FTE Tech: 0.25 FTE Assembly and integration of all target systems and final leak tests and vacuum acceptance tests at ESS (labor) 250 k€ Eng: 0.8 FTE Designer: 0.6 FTE Tech: 2.75 FTE Monolith Vacuum Hardware, rough vacuum All hardware 2 bar radiations resistant. 300 k€ Instrumentation feed-throughs and windows 30.0 k€ Delta vacuum equipment cost for upgrading 2 bar gauge pressure operation + radiation resistant 80 k€ Vacuum support equipment 100 k€ Vacuum Control System (non-labour and labour) 90 k€ Eng: 0.25 FTE Tech: .50 FTE Total cost rough vacuum, 2 bar gauge pressure operation 1 149.2k€ Eng: 3.35 FTE Tech: 3.50 FTE Monolith high vacuum up-grade to allow removal of PBW Delta vacuum equipment cost for upgrading to high vacuum 350 k€ Required upgrades to accelerator Including the Pressure code compliance Steady state operation includes: 0.5 FTE Eng + 1 FTE tech Operational Spares Operational year 2021 2022 2023 2024 2025 Value [k€] 105.0 95.0 115.0 145.0 135.0

5 MRV System as CDR version
Total labour ( ): Eng: 6 FTE (include designer) Tech: 9 FTE (installation) Total hardware ( ): Service: 280 K€ (contractors) Mat: 875 k€ (equip+controls)

6 Early schedule for Monolith installation
Only high level milestone available from P6 First time we need vacuum tests during installation of monolith 7th of Feb 2020. - Leak test of the Proton Beam Vessel Monolith rough vacuum system fully functional (System test performed), 1st march 2022 - First pump down fully loaded and leak tested

7 Top view Dec -19 (Temp crane op.)
Temp crane 65 ton

8 Monolith Vessel installation
Access route for portblock installation

9 High bay Crane for Target installation period
Preferred solution 2 x 65 Ton Temporary cranes Temp. crane 65 ton Operational jan -20 Temp. crane 65 ton Operational dec -19 Or Permanent crane 95ton Cleanliness during installation inside monolith (same requirements for temp. Crane as for permanent crane) Speed (traverse and hoist) suitable for installing heavy sensitive components True vertical lift (might not be a requirement for temp. crane, Allow to have parallel work on both area (building won’t be fully close during the installation inside monolith)