Army Team C4ISR BRAC Update
Presented By: Sue Nevin, G3/5 CECOM Life Cycle Management Command 8 October 2009
2
What We’ve Done Phased Relocation Status and Timeline (FY07 – FY11)
1, “Boots on the Ground” Groundbreaking For Permanent Facilities Time Now Phase 1 Early Relocation 32 positions (11 Vol.) Phase 2 Early Relocation 340 positions (140 Vol.) Phase 3 Early Relocation 1317 positions (542 Vol. Currently) Main Moves Into Permanent Facilities 2007 2008 2009 2010 2011 2012 In accordance with Report to Congress and BRAC Strategic Plan: Developed Phased Early Relocation strategy using temporary facilities at APG – combination of military, civilian volunteers, new hires and contractors Page 2 of 29 2
3
Estimated Move In Dates Mission Training Facility
MTF GMS TOWER C2/CNT WEST GMS LAB HQ BES WEST HQ BES EAST Auditorium Phase 1 Estimated Move In Dates Domains GMS Lab 1 Aug 10 Ground Based Radars, Multi-Intel, Sensors, Force Protection (FP), Night Vision (NVEO) GMS Tower HQ East 1 Oct 10 HQ, Business Enterprise Systems, Operations Support HQ West Auditorium C2/CNT West 1 Nov 10 Command & Control (C2), Navigation, Future Combat System (FCS) Mission Training Facility Page 3 of 29
4
GMS Lab & GMS Tower Estimated Date that Moves will begin: 1 August 2010 Building Occupancy: 1,410
5
HQ East & HQ West Estimated Date that Moves will begin: 1 October 2010
Building Occupancy: 2,143
6
C2/CNT West & Mission Training Facility
Estimated Date that Moves will begin: 1 November 2010 Building Occupancy: 1,800
7
Estimated Move In Dates
Army Team C4ISR Phase II Building Occupancy: 2,213 Consolidated North Power & Cooling C3/CNT East JSEC Phase 2 Estimated Move In Dates Domains C2/CNT East 1 Mar 11 Comm System Network Transport (CNT) Consolidated North C3T SPO, CECOM Safety Power & Cooling (5100) Power and Cooling (P&C) JSEC C2 Integration 15 Jul 11 Fabrication