Download presentation
Presentation is loading. Please wait.
2
A Safety Overview of the HIE-ISOLDE Project
AP.Bernardes, A.Dorsival, S.Giron, D.Phan, J.Vollaire, D.Voulot ESS Seminar
3
Outline Introduction to ISOLDE and to HIE-ISOLDE
Radioprotection issues Cryogenic safety issues General safety issues Target failures 10/06/2014 ESS Seminar
4
Outline Introduction to ISOLDE and to HIE-ISOLDE
Radioprotection issues Cryogenic safety issues General safety issues Target failures 10/06/2014 ESS Seminar
5
Introduction Proton beam from PSB: 1.4 GeV 2 µA 3e13 protons/pulse
Cycle: 1.2 s 3 kW average power Instantaneous power: ≈ 1 GW 10/06/2014 ESS Seminar
6
Introduction Existing Facility
Selectivity Isolde Protons 1.4GeV HRS GPS GPS: M/ΔM=2400 HRS: M/ΔM=5000 Acknowledgment E.Siesling GPS HRS 10/06/2014 ESS Seminar 6
7
Introduction Existing Facility
Beam dump Target Front- End ISOLDE is an Isotope Separator On Line facility dedicated to the production of a large variety of radioactive ion beams Radioctive ions beams Experimental area By definition we cannot “enclose” 100% the target with a double envelope Front-end Coupling table Target 10/06/2014 ESS Seminar 7 7
8
Introduction HIE ISOLDE project
Increase of protons beam Intensity (HI Design Study) Protons/pulse Intensity μA Energy GeV Cycles Power kW* 2.2 1.4 1.2 3.1 1.1014 6.7 2 13.3 50% of pulses from booster Increase Energy of radioactive ions beams (HE - October 2015) REX-LINAC – 3MeV/u Supraconducting LINAC – 10MeV/u 8 10/06/2014 ESS Seminar 8
9
Introduction HE upgrade
HIE SC Linac High Energy Beam Transfer lines HEBT Compressor building 198 Cold Box building 199 HIE-ISOLDE Facility High Energy upgrade Upgrade existing post-accelerator 3MeV /u with HIE SC supraconducting LINAC Stage 1 5.5 MeV/u Final stage 10 MeV/u for A/q=4.5 9 10/06/2014 ESS Seminar 9
10
Introduction HE upgrade
Compressor building 198 Cooling & Ventilation: finished. Tests demineralized water ongoing. Cryogenic: Piping done. Compressor frame installed
11
Introduction HE upgrade
Power distribution racks in place. Air ducts all in place Cryo: Cold box under refurbishment Cold Box building 199
12
Introduction HE upgrade
Stage 1 Acknowledgement S. Maridor Cryo Module 1: June 2015 Cryo Module 2 installation: Shutdown 2015/16: Jan – March 2016
13
Introduction HE upgrade
Superconducting LINAC - 6 cryomodules - 32 cavities QWRs Quarter Wave Reasonators geometries MV of total effective acceleration voltage
14
Introduction HE upgrade
Thermal shield Vacuum vessel RF Cavity - Accelerating gradient 6MV/m MHz Niobium-sputtered copper Helium vessel (150l LHe) Solenoid Solenoid
15
Introduction HE upgrade
Accessible experimental area 3 HEBT (High Energy Beam Transfer) lines 6 magnetic dipoles 45° 24 magnetic quadrupoles
16
HSE Health, Safety and Environment Unit
Introduction HIE-ISOLDE organisation 45 MCH Budget 1 MCH Budget HSE Health, Safety and Environment Unit Progress on Safety is reported at: HIE-ISOLDE project management Steering committee International Advisory Panel Safety review
17
Outline Introduction to ISOLDE and to HIE-ISOLDE
Radioprotection issues Cryogenic safety issues General safety issues Target failures 10/06/2014 ESS Seminar
18
Radioprotection issues
Radiological risks with the new LINAC X-ray from cavities Use of Stable Beam Nuclear interactions lead to the production of penetrative secondary particles (neutrons & gammas) Use of RIB Radioactive Ion Beam Implantation of RIB (“hot-spot” build-up, contamination risk when opening the vacuum chamber for maintenance) Minor compare to low Energy part
19
Definition of X-Ray sources was needed
Radioprotection issues X-ray from cavities (operation & conditioning) Strong source of bremsstrahlung X-rays in some operating conditions Depends on surface state and cleanliness of the cavity Definition of X-Ray sources was needed ORSAY Acknowledgment S.Giron and J.Vollaire/DGS-RP
20
Radioprotection issues
Measurements (contact): Normal operation: few mSv/h RF conditioning: 20 mSv/h He processing: 350 mSv/h Used to size LINAC shielding 350 mSv/h FLUKA simulation: Rate of electron production due to “field emission” Acknowledgment S.Giron and J.Vollaire/DGS-RP
21
Radioprotection issues
Acknowledgment S.Giron and J.Vollaire/DGS-RP 300 μSv/h 10 μSv/h Identification of weak point Validation of shielding 40-50 μSv/h Mitigation measures: - RF cavities in a shielded enclosure (supervised area <3 μSv/h) No access to the personnel during operation X-Ray monitoring with RP alarm outside shielding Access forbidden to the roof Additional shielding at each extremities
22
Radioprotection issues
Use of Stable Beam Beam setting done with higher intensity stable beam (before each radioactive beam) Diagnostic box inserted to the beam may created a local “hot spot”
23
Radioprotection issues
Use of Stable Beam Nuclear interactions lead to the production of penetrative secondary particles (neutrons & gammas) He 19.8 MeV/amu Acknowledgment : J.Vollaire DGS/RP
24
Radioprotection issues
Acknowledgment : D.Voulot BE/OP FLUKA simulation He2+ 1 ppA 20 MeV/u (J. Vollaire) L. Moritz, “ISAC II Safety Report”, TRIUMF, 2006 08/04/14 AP.Bernardes EN-STI
25
Radioprotection issues
Maximum intensities for 3 µSv/h at 1 m maximum energy Operational table giving maximum intensity allowed on stable beam Operation engineer in charge of machine responsible to respect the maximum beam intensities Acknowledgment : D.Voulot BE/OP
26
Outline Introduction to ISOLDE and to HIE-ISOLDE
Radioprotections issues Cryogenic safety issues General safety issues Target failures 10/06/2014 ESS Seminar
27
Oxygen Deficiency Hazard and potential exposure to cold burns
Cryogenic safety issues Each cryomodule contains 150l of LHe at 4.5K at 1.3 bara – 900 liters in total – Tunnel 300 m3 Access requested inside tunnel when cryomodules are cold (steady-state) Oxygen Deficiency Hazard and potential exposure to cold burns 150 liters LHe Acknowledgment : Y.Leclercq 10/06/2014 ESS Seminar
28
Pressure relief devices are routed outside the tunnel.
Cryogenic safety issues Risk assessment Scenario: Unexpected vacuum break Release of He through burst disk located on LHe tank Safety devices on liquid Helium tank will release He outside of the HIE-ISOLDE tunnel Tunnel roof Ghe volume Relief valve Burst disc Lhe volume 0. Nominal conditions 1. Vacuum break Acknowledgment : Y.Leclercq and D.Phan 2. Air in-flow to the VV 3. Heat transfer to cold surfaces 5. P increase & devices opening Pressure relief devices are routed outside the tunnel.
29
Cryogenic safety issues
Risk assessment Design 2: Burst disk on insulation vacuum located at the top of cryomodule routed outside tunnel Design 1: Burst disk on insulation vacuum located at the bottom of cryomodule not routed outside tunnel – Compensatory measures needed Due to space constraint on the top plate, design 1 was selected and presented at the safety review
30
Cryogenic safety issues
Volumetric concentration of O2 [%] Temperature [K] Access only on one side and protective screen between burst disk and work place AP.Bernardes EN-STI 30
31
A change from design 1 to design 2 was requested by the safety review
Cryogenic safety issues Risk assessment Scenario: In nominal operation, the cold mass is cooled down to 4.5K and the pressure in the LHe circuit is 1.3bara. The adjustment mechanisms are operated to re-align the superconducting components. This leads to a full rupture of the biggest bellows. Safety devices on Vacuum vessel tank will release He outside of HIE-ISOLDE tunnel 0. Nominal conditions Tunnel roof 1. Bellows rupture A change from design 1 to design 2 was requested by the safety review 2. Pressure increase 3. Relief devices opening Updated layout: Pressure relief devices are routed outside the tunnel. Relief pressure valve Burst disc Ghe-Lhe volume Thermal shield Vacuum vessel Path of helium gas Bellows rupture 10/06/2014 ESS Seminar
32
Cryogenic safety issues
Safety pressure device on insulation vacuum routed outside Safety pressure device on LHe tank routed outside 10/06/2014 ESS Seminar
33
Outline Introduction to ISOLDE and to HIE-ISOLDE
Radioprotections issues Cryogenic safety issues General safety issues Target failures 10/06/2014 ESS Seminar
34
General safety issues Cern boundary Distance < 100m from CERN Boundary and offices building Offices building
35
General safety issues 2 cooling towers External Noise Sources:
2 chillers Bld. 198 Bld. 170 Air inlet – Building 198 Air inlet – Building 199 Bld. 199
36
General safety issues Internal noise Sources: Ventilation units
2 compressors Ventilation units
37
Acoustic panels on walls
General safety issues Acoustic doors Acoustic treatment for building 198: Acoustic panels on walls Roof treated Acoustic baffle on inlet air for ventilation units 10/06/2014 ESS Seminar
38
General safety issues - Noise at CERN boundary complying with the legal value - Noise at the level of windows office under acceptable tolerance 10/06/2014 ESS Seminar
39
General safety issues Infrastructure and sensitive equipment shall be designed following CERN Seismic Safety rules: The French territory is divided in five seismic zones from very low seismicity (seismic zone 1) to strong seismicity (seismic zone 5) – EDMS CERN is classified as seismic zone 3 – Moderate seismic Hazard 10/06/2014 ESS Seminar
40
General safety issues HIE-ISOLDE tunnel – Concrete blocks piling structure 10/06/2014 ESS Seminar
41
General safety issues LMGC90 modele Minor change on the structure for a seismic type E (few millimeters of move without any impact on the tunnel stability) Acknowledgment consultant Résonance and E.Perez-Duenas 10/06/2014 ESS Seminar
42
General safety issues Study demonstrated that we have a reserve capacity of a factor 2 for the stability of the tunnel in case of seismic event
43
Outline Introduction to ISOLDE and to HIE-ISOLDE
Radioprotections issues Cryogenic safety issues General safety issues Target failures 10/06/2014 ESS Seminar
44
Solid inside container Liquid inside container
Target failures Solid inside container – ISO GPS beam – 3.3.E13 protons per pulse 4 bunches per pulse 572 ns in between each bunch Fragmentation, Spallation, Fission Liquid inside container – STAGISO beam – 1.E13 protons per pulse 3 bunches per pulse 16 μs in between each bunch ISO GPS beam instead of STAGISO on liquid target Container weld have cracked release inside vessel of irradiated Pb 10/06/2014 ESS Seminar
45
Target failures ISOLDE operator in charge choses the parameters of the beams STAGISO or ISO GPS beam : Beam intensity is measured between injection and acceleration. If value > 1E13 protons per pulse (for STAGISO) then beam acceleration is “killed” in 1ms Average (3 mn) number of particles monitored with BCT (Beam Current Transformer) If ppp> 1.E13 (for STAGISO), beam injection is stopped 10/06/2014 ESS Seminar
46
Fragmentation, Spallation, Fission
Target failures Fragmentation, Spallation, Fission Tantalum converter Target container Container Target receiving 2.5.E18 protons with a focused proton beam 3.E13 n n n n 10/06/2014 ESS Seminar
47
Water cooling leak test
Target failures Cooling water leak on target: Oxydation of tantalum, molybdenum… Production of H2 Water cooling leak test 10/06/2014 ESS Seminar
48
Broken flange on Front-end due to corrosion:
Other failures Broken flange on Front-end due to corrosion: 10/06/2014 ESS Seminar
49
Other failures Failure of target rotation mechanism of CNGS target 2010: 6.7*1019 POT 2.7 MGy - Rust/pitting corrosion due to use of low grade X46Cr13 balls - ZrO2 bearings tested and presently under analysis 2012: 3.9*1019 POT ~2.0 MGy Acknowledgement M.Calvani 10/06/2014 ESS Seminar
50
Thank you for your attention
51
5th High Power Targetry Workshop
Back up slides E.Noah et al., Eurisol 100 kw target stations operation and implications for its proton driver beam*, Proceedings of EPAC 2006, Edinburgh, Scotland 22/05/2014 5th High Power Targetry Workshop
52
Back up slides MD beam 500 epA
Use Ne5+ instead of He+ Same A/q Easier to produce Lower dose rate L. Moritz, “ISAC II Safety Report”, TRIUMF, 2006 Acknowledgment : D.Voulot BE/OP
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.