Possessions Update Great Western Railway Andy McRae
Senior Possession Delivery & Communications Manager 26 June 2019
2
GWR Possession Team Comprehensive business readiness service
Dedicated Project Manager, supported by up to eight departmental representatives Focus on customer experience, communications, robust plan Adherence to timescales, cost efficiency, continuous improvement Consistency GWR/NR alliance
3
2018 – The Year of Transformation
27 weekday blocks affecting much of the GWR network: New signalling in Bristol and Filton 4-tracking Electrification Didcot to Bristol Parkway Patchway/Severn Tunnel Junction area electrification Flood alleviation in Devon North Cotswolds platform extensions Oxford track works/signals Electrification to Newbury Westbury North Jct renewal
4
2019 – The Year of Maintenance
- 8 weekday possessions - 11 “significant” weekends - 135 “other” weekend possessions Whiteball tunnel concrete lining Bedminster and Avon Valley Track renewals Gloucester West Junction renewal Tarka Line track renewals Cogload Junction renewal South Wales electrification
5
Christmas 2019 24-27 Dec – Affects trains to/from London Paddington
25 Dec to 1 Jan –Newport junction renewal 25-31 Dec – Guildford Bridge repairs 25-27 Dec – Exeter St Davids track renewals
6
Notable possessions in 2020
From Jan - 80 miles of track renewals in WofE Feb - Hayle viaduct plus St Erth, Penzance and Camborne stations – 9 days Feb – Barnstaple branch structures work – 6 days Mar – bridge work Castle Cary-Taunton – 16 days Mar – track renewals West Ealing – Sunday nights Apr – Westbury avoider track renewals – 4 days Apr – Gipsy Patch Lane bridge widening – 12 days From May – Bristol East enabling works From May – track renewals from Newton Abbot west Aug – Swindon to Bristol Parkway track lowers Oct to Nov – Exmouth Junction Dec – Truro-Penzance – 4 days Dec to Jan – Bristol Temple Meads roof refurb – 16 days
7
Notable possessions in 2021
Jan – HS2 works commence Jan to Feb – St Ives branch track renewals – 35 days Feb to Mar – bridge renewal – 16 days Liskeard to Truro Jun to Sept – Bristol East junction renewal Sept – Bristol Temple Meads roof refurb – 16 days
8
Year on year comparison
2016 2017 2018 2019 2020* 2021* Weekday Blocks 6 13 27 8 9* 10* “Significant” Weekend Blocks 11 Not yet categorised “Other” Weekend Blocks 3 44 55 135 80* 156* Total Managed possessions 9 57 82 152 89* 166* * Various possessions still TBC
9
Activity affecting TransWilts
Salisbury to Southampton closed 21/22 Sept, and 27 Oct Warminster to Southampton closed 29 Sep, 19/20 Oct, and Dec Frome to Taunton closed 19/20 Oct No further Melksham line closures in 2019 2020 Four consecutive Sundays in January for bridge repairs Two weekends in October for Melksham drainage work
10
Communication strategy
Focus on: Point of Sale Journey Checkers (GWR.com, NRES) Posters at targeted locations Transformation Displays
11
Communication strategy
Focus on: Stakeholder engagement Community Rail initiatives Link into the December timetable
12
December 2019 Timetable Change
Realising the potential of electrification and the full benefit of Intercity Express Trains: New services Greater frequency Faster journeys Possession activity remains key