1 Dixon Middle School Project Update
MEASURE Q Dixon Middle School Project Update Presented By: John Calise Director of Facilities, Operations and Capital Projects March 28,2018

2 OLD DHS DIXON MIDDLE SCHOOL

3 Initial Facility Assessment
Full Modernization 21st Century Learning Environment Total Program Cost Developed by DUSD, LPA & Cumming April 2016 Construction Cost $ 22,704,000. Total Project Cost $ 29,813,000. Consumed all Bond Proceeds Consumed Bonding Capacity Unrealistic Budget and Project Scope!

4 Create a Safe and Effective Learning Environment
Alternative Approach Create a Safe and Effective Learning Environment

5 Alternative Approach Internal Capacity
Internal Maintenance and Construction Services Projects Existing Home Economics Rooms Convert to Staff Lounge Convert to Staff Work and Meeting Room Central Kitchen Stage Area Multi-Purpose Room Some Exterior Dry Rot Small Gym

6 Defining the Scope Schematic Design

7 Schematic Design (continued)

8 Project Reassessment Targeted Modernization
Create an Environment that is Conducive to Learning Accessible Compliant Safe Clean Comfortable

9 Refined Budget Furnishings and Equipment Re-Roof A-Wing
Construction Costs Soft Costs (29% of total project including F&E Design) Total Bond Funding for the DMS Project $1,500,000. $ 500,000. $9,625,000. $3,375,000. $15,000,000. Agreement reached with architect for SD for F&E as well as with manufacturers to provide this moving forward.

10 Soft Costs Expenses that are not considered direct construction costs
Architectural Fees Engineering Fees Inspection Services Testing Labs Legal Fees Consultants These are the big examples but this list is NOT ALL INCLUSIVE

11 Design Development Working within the parameters of the budget
Fire/Life Safety Accessibility Compliance Vandalism Building Envelope Climate Control F & E Acceptable Classrooms

12 DD – Original Basis of Design
Element Area Cost / SF Total Building A 19,708 $99.10 $1,953,062.80 Building B 9,500 $105.71 $1,004,245.00 Building C 16,121 $140.44 $2,264,033.24 Gymnasium (Entry, Bleachers and RR Only) 19,357 $93.08 $1,801,749.56 MPR 16,145 $37.32 $602,531.40 Music 4,563 $93.76 $427,826.88 Quad Restrooms 668 $279.46 $186,679.28 Site Work $1,429,301.84 Cost Estimate for Original Basis of Design $9,669,430.00 Point out at this point in time - $50k over original DD Cost Estimate

13 Do it Right the First Time
Long Term Occupancy 30 Year+ Plan Every Student in the District who is currently in or under the 3rd grade will attend this school Identify Scope Not Included in the DD Set Identify Need to Add Scope Consider the Costs of Additional Scope Consider the Returns of Additional Scope

14 Additional Scope

15 Administration Area (vision)

16 Administration Area (conceptual)

17 Existing Space (conceptual)

18 Existing Space (conceptual)

19 Existing Conditions

20 Existing Conditions

21 Why? Original Design – Open Campus Safety and Security
Access Control Existing Administrative Areas Not ADA Compliant Does not Align with a Middle School Large Amount of Water Damage Mold Remediation Required Doing it Right the First Time!

22 Modernize Boys Locker Room (conceptual)

23 Why? Locker Room – Not ADA Compliant Bathroom – Not ADA Compliant
Coaches Office – Not ADA Compliant Additional PE Storage Addition of a Guest Locker Room Accessible from the Exterior Sectioned off from the Boys Locker Room Doing it Right the First Time!

24 Modernize Girls Locker Room (conceptual)

25 Why? Locker Room – Not ADA Compliant Bathroom – Not ADA Compliant
Coaches Office – Not ADA Compliant Addition of a New Point of Entry Accessible From the Interior of the Gym Eliminates Need for Supervision Between Locker Room and Gym Doing it Right the First Time!

26 New HVAC System for Large Gym
WHY? Current System is Heating Only Addition of Air Conditioning Current Boiler in Poor Repair Air Handlers 2 Not Functioning Piping Leaks Student and Staff Comfort Doing it Right the First Time!

27 Convert Locker Rooms to Restrooms in Small Gym

28 Why? Locker Room – Not ADA Compliant Bathroom – Not ADA Compliant
Fixture Count Small Gym Used as an Extension of the MPR Food Service Assemblies Special Events Doing it Right the First Time!

29 Recommended Alternates

30 Replace HVAC System in the MPR Bldg.

31 Existing Conditions

32 Existing Conditions

33 Why? Existing Heating System is Antiquated and in Poor Repair
Existing Cooling System is Inoperable System Supports Various Spaces Gymnasium MPR Food Service Central Kitchen Staff Work and Meeting Room Staff Lounge Classroom Space Doing it Right the First Time! This Building is 19,850 Square feet. Roughly the same size as A-Wing

34 Replace Existing Small Gym Floor with Sport Court Flooring System

35 Why? Existing Gym Floor in Poor Repair
MPR Tables will Destroy Existing Wood Floor Small Gym to be used as an extension of the MPR Room Various Designs Create additional Options for PE Basketball Futsal Volleyball 4 Square Classroom Space Doing it Right the First Time!

36 How Much is it Going to Cost?
Element / Scope Justification Sub-Total Total Cost Estimate for Original Basis of Design $9,669,430.00 Convert Locker Rooms to Restrooms in Small Gym Meet the required fixture count $319,500.00 New HVAC system on the large gym Sub-committee Directed $248,145.00 Consolidate administration area in A-Wing to entry Required to create a secure campus $322,833.00 Modernize Locker Rooms (Large Gym) $1,025,790.00 Total - Scope Increases $1,916,268.00 MPR HVAC Existing system is antiquated $1,093,888.00 Sport Court Flooring (Small Gym) Extension of MPR $183,303.00 Total - Deductive Alternates $1,277,191.00 Total Construction Cost Estimate through 12/18 $12,862,889.00 Soft 25% $3,215,722.25 A-Wing Roof $500,000.00 Balance $16,578,611.25 Furnishings and Equipment $1,500,000.00 Bond Allotment $15,000,000.00 Shortfall -$3,078,611.25 Note: Does not include construction contingency (recommended 15%)

37 How Do We Fund It? Developer Fees?
Fire/Life, Safety, ADA Contribution? General Fund Contribution? One Time Money? Facility Hardship Program? Consulting Fees Process Through OPSC Process Through Local Legislators Process Through SAB $1,035,561 of Existing Estimate is for Fire /Life Safety and ADA Ramps Proposal for Facility Hardship Program Roughly $6500. to process and an additional $17500 to advocate if necessary No Guarantee on outcome. Paid from General Fund

38 Room For Growth? Current conditions can house 750 Students
27 Classrooms , 2 Gymnasiums, Stage/MPR, Music Building

39 How Does the Campus Grow?

40 Future Growth 2 story Modular construction. 8 packs = 7 classrooms + 1 pod (in each) for restrooms or offices/meeting rooms, etc. Allows DMS to grow/expand 182 students at a time (without classroom sharing) Average cost in 2017 $ = $ $300. per square foot Each Building Average in 2017 $ 2.15M

41 Questions/Discussion