Facility Improvement Program Report
Construction Projects Updates By Leonard Kahn CBO & Facilities and Planning Department
2
Projects Completed Project Name Approved Budget Final Cost
Quick Start Projects – Painting Bear Creek High $1,200,000 $448,337 McNair High $1,000,000 $538,458 Quick Start Projects – Roofing Joe Serna $680,000 $663,889 Westwood $800,000 $662,540
3
Projects In Construction
Project Name Approved Budget Current Cost Tokay High Stadium Project Field & Truck Renovation $5,645,000 $2,734,078 New Bleachers $3,000,000 $538,458 Anticipated Completion Date: November, 2018
4
Projects In Design New Maintenance Operation Yard
M&O Facility Done N/A 11/ / $16 Million
5
Projects In Design New and Modernization Projects
Lodi High 02/ / / / $62,000,000 Tokay High 10/ / / / $27,000,000 Needham ES 04/ / / / $14,000,000 Houston ES 06/ / / / $3,200,000
6
Projects In Design Fire Alarm Upgrade Projects
Lodi Middle Completed Approved 01/ / $546,000 Bear Creek High 12/ / / / $1,953,000 Heritage ES 12/ / / / $620,000 Parklane ES 12/ / / / $630,000 Wagner Holt ES 12/ / / / $630,000 Victor ES 12/ / / / $163,000
7
Other Projects Lockeford School Parking Lot Addition
8
Other Projects Storm Water Pump Station
McNair High 06/ / / /2019 $3,000,000
9
Completed Projects Unused Amounts
…8200 LUSD Board of Trustees may expect to see Budget Transfers from completed projects into the Resource Management Code.