Building 360 Freight Elevator Rehabilitation at SSWRF
Award Contract S06038C03 Building 360 Freight Elevator Rehabilitation at SSWRF Commission Agenda Item #4
2
Filter Press Building Freight Elevator
Elevator is original to Filter Press Dewatering Building Used more than 25 years Important to efficient operation and maintenance
5
Elevator Issues Elevator does not level properly Currently inoperable
Cylinder/plunger assembly Failed Needs to be replaced Situated inside underground casing
6
Proposed Contract Scope of Work
Remove existing cylinder/plunger assembly Remove existing casing Install new casing Install new cylinder/plunger into new casing
7
Elevator Components Shaft Car Replace Plunger Replace Cylinder
Replace Casing
8
Project Cost/Schedule
Contract within budget Contract duration 275 days