1 Building 360 Freight Elevator Rehabilitation at SSWRF
Award Contract S06038C03 Building 360 Freight Elevator Rehabilitation at SSWRF Commission Agenda Item #4

2 Filter Press Building Freight Elevator
Elevator is original to Filter Press Dewatering Building Used more than 25 years Important to efficient operation and maintenance

3

4

5 Elevator Issues Elevator does not level properly Currently inoperable
Cylinder/plunger assembly Failed Needs to be replaced Situated inside underground casing

6 Proposed Contract Scope of Work
Remove existing cylinder/plunger assembly Remove existing casing Install new casing Install new cylinder/plunger into new casing

7 Elevator Components Shaft Car Replace Plunger Replace Cylinder
Replace Casing

8 Project Cost/Schedule
Contract within budget Contract duration 275 days

9 QUESTIONS?