1 LIU-SPS review for BI (no BWS)
Systems – active: Orbit system upgrade Optical fibre infrastructure (EN-EL) BSRT tank Internal beam dump Budgets and EVM Outlook with open actions Lars Jensen - on behalf of BE/BI 25/09/2019

2 SPS Orbit upgrade (64046) (700 kCHF)
2019: System review (January’19) (Chaired by Brennan) Outcome: Need asynchronous mode for initial commissioning Need interlock specifications (under approval) New system is baseline for start-up (no splitters) LS2: Full production review during June 2019 First sector installed end of 2019 Full system installed by mid 2020 2021: Beam commissioning Budgets: Analogue front-end more expensive than expected (more iterations required) Design cost: 15k -> 58k Production cost: 180k -> 285k Misc: > 60k New cost to completion = 823k 25/09/2019

3 Optical fibre infrastructure (EN-EL) (64724)
Installation believed to be on schedule and within budget EN-EL-FC (J. Blanc to confirm) 25/09/2019

4 BSRT (LSS5) - 64042 BTV for TPSC4 – 64042 (40kCHF)
Done: Mechanical design for LSS5 solution (516) (BI/MME) complete .. To do (LS2): Launch ECR for approval Produce tank and support (MME to announce price) Expected ready for installation Q1/2020 BTV for TPSC4 – (40kCHF) Unfunded TE-ABT request Cables and camera ordered To do: 2019: produce mechanics Installation date? 25/09/2019

5 Internal beam-dump for BI (64045)
Status New vacuum layouts for LSS1 and LSS5 complete DIC/DEC requests updated (EN-EL) Final estimates following system relocation pending BTV upstream of dump (total cost ~100k) Done: Majority of orders committed LS2: Produce tank, install and hardware commission Budgets: CtC 250 kCHF all committed Need another 20kCHF to finalise project (open question about cable cost) 25/09/2019

6 Budgets and EVM EVM curve 25/09/2019

7 Outlook with open actions
On-going: SBDS for BI on track (+20kCHF) Fibres on track (EN-EL to confirm) BSRT (MME production) TPSC4 on track MOPOS upgrade (+120kCHF) Open actions: .. 25/09/2019