1 ATS Consolidation Day 22nd May 2019 Beam Instrumentation
Rhodri Jones (BE-BI)

2 Introduction Beam Instrumentation Consolidation Domains
Replacement of outdated electronics ~ 20 years lifetime for most systems Beyond this maintenance & repair is difficult Increasing number of failures Components required no longer available Rely on limited stock of spares Replacement of radiation damaged components Beamline components typically over 20 years old in high radiation areas Spares for mechanical systems Project started during LS1 to identify all beamline components & class then in terms of risk to operation Critical items identified & being consolidated on all machines 2019 ATS Consolidation Day R. Jones – BE-BI

3 2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019
PS complex & AD No. Activity / Workunit STATUS [EDMS] Description & Consequences 1 BTV Acquisition Electronics Renovation Active Replacement of outdated electronics – repair no longer possible. Replace with new electronics. 2 Consolidation of ISOLDE BI Mechanics Missing Consolidation of 7 very old transformers in L2 (L4) transfer line & 5 in Booster Injection line 3 Consolidation of PSB BTV mechanisms Profit from production of new bellowless design for LIU to consolidate all PSB screen mechanisms 4 Mechanical Spares for Critical PS Systems Construction of spare parts for operationally critical BI. Full inventory in LS1 resulted in prioritised list with input from OP. Additional budget added to complete. 5 Consolidation of AD Electron Cooler Consolidation options recently reviewed – awaiting final report. Current budget foresees complete replacement of existing cooler. Schedule/ BUDGET [kCHF] No. 2019 2020 2021 2022 2023 2024 2025 SUM 1 100 30 57 187 2 3 412 4 70 50 150 80 450 5 500 1200 509 2309 2019 ATS Consolidation Day R. Jones – BE-BI

4 PS complex & AD (New requests) Replacement of Analogue Cameras
No. Activity / Workunit STATUS [EDMS] Description & Consequences 1 Replacement of Analogue Cameras New Missing 270kCHF (awarded ) to buy all remaining spare tube cameras in stock. Need to foresee complete replacement of analogue cameras by digital cameras 2 3 4 5 Schedule/ BUDGET [kCHF] No. 2019 2020 2021 2022 2023 2024 2025 SUM 1 2 3 4 5 2019 ATS Consolidation Day R. Jones – BE-BI

5 SPS complex (Approved Activities)
No. Activity / Workunit STATUS [EDMS] Description & Consequences 1 Consolidation of SPS SEM Electronics Active Replacement of outdated electronics – repair no longer possible. Replace with new electronics. Electronics already consolidated in PS complex 2 Mechanical Spares for Critical SPS Beam Instrumentation Missing Construction of spare parts for operationally critical BI. Full inventory in LS1 resulted in prioritised list with input from OP. May need additional budget. 3 SPS DCCT & Transfer Line FBCT Replacement Currently relying on industry with service contract. Will pay for itself in long run, need to cover both contract & development in short term 4 Consolidation of SPS Ring BLM System Was LIU-SPS but cannot be done until after LS2 (manpower constraints). SPS system already showing signs of degradation. Urgent request from OP & MPP for additional protection. Schedule/ BUDGET [kCHF] No. 2019 2020 2021 2022 2023 2024 2025 SUM 1 150 50 2 70 105 345 3 100 60 160 4 20 250 200 180 900 2019 ATS Consolidation Day R. Jones – BE-BI

6 SPS complex (New Requests)
No. Activity / Workunit STATUS [EDMS] Description & Consequences 5 Consolidation of TT2/TT10 Transfer Line BPM Electronics New Missing Replacement of outdated electronics – repair becoming problematic. Replace with same electronics as SPS Ring. Need early decision to profit. 6 Consolidation of TI2/TI8 Transfer Line BLMs Based on old SPS BLMs & electronics. Consolidate at same time as SPS ring system (LS3) or LHC (LS4) 7 SPS & Transfer Line BLM ionisation chamber replacement Not originally foreseen in SPS BLM consolidation. Degradation of existing monitors & lack of spares imply 750 new monitors required for SPS consolidation. Proposed to be funded through in-kind Russian contribution as part of HL request 8 Consolidation of SPS Ionisation Profile Monitor (BGI) Replacement of current system based on MCP and radiation tolerant camera with system based on LIU-PS TIMEPIX solution. Reduces maintenance costs (MCP & camera ageing) while adding performance. Schedule/ BUDGET [kCHF] No. 2019 2020 2021 2022 2023 2024 2025 SUM 5 100 200 50 350 6 80 630 7 1100 8 120 190 360 2019 ATS Consolidation Day R. Jones – BE-BI

7 East Experimental Area
No. Activity / Workunit STATUS [EDMS] Description & Consequences 1 Consolidation of East Area Beam Instrumentation Active Consolidation as part of general East Area CONS 2 Consolidation of East Area multi-wire proportional chambers No longer possible to easily maintain MWPCs or produce new ones. Will be replaced by scintillating fibre monitors developed for EHN1 (XBPF) 3 Consolidation of East Area BLM system Partial Funding Schedule/ BUDGET [kCHF] No. 2019 2020 2021 2022 2023 2024 2025 SUM 1 33 50 11 94 2 23 30 53 3 2019 ATS Consolidation Day R. Jones – BE-BI

8 North Experimental Area (Primary Lines)
Activity / Workunit STATUS [EDMS] Description & Consequences 1 BSI and BSP Foil Monitor Renovation New Consolidation of 8 foil monitors used for intensity and position monitoring. Degradation due to radiation and ageing electronics 2 Student for BSI and BSP Foil Monitor Renovation Doctoral student to study SEM processes for high intensity beams. Possible collaboration with Liverpool (UK) 2Y CERN funding & 2Y Liverpool. 3 BTV Monitor Consolidation Consolidation of 3 radiation damaged BTV systems to modern standards using optical line & digital cameras. 4 Consolidation of North Area BLM system Consolidation of BLMs. Ageing system already leading to SPS NA Physics downtime. Urgent, minimal, temporary intervention to ensure functioning to LS3 carried out in LS2. Schedule/ BUDGET [kCHF] No. 2019 2020 2021 2022 2023 2024 2025 SUM 1 50 160 240 150 600 2 44 88 3 70 100 220 4 40 TOTAL (kCHF) 1148 2019 ATS Consolidation Day R. Jones – BE-BI

9 North Experimental Area (Secondary Lines)
Activity / Workunit STATUS [EDMS] Description & Consequences 1 Consolidation of North Area Electronics Draft 3 Ageing electronics. Already running with hardware patch to allow old cards to run with new processors under Linux. New estimate up from 500kCHF to 755kCHF 2 Consolidation of 65 Wire Chambers & FISCS with XBPF (scintillating fibre monitor) No longer possible to easily maintain MWPCs or produce new ones. XBPF proven to be viable alternative in EHN1. Original request for 200kCHF to consolidate some in LS2 not granted. New request covers all 65 monitors in LS3 for 1890kCHF. 3 Urgent Consolidation for Post LS2 Running New Items identified as urgent to consolidate during LS2 4 Consolidation of XSCI & XCET Various smaller consolidation items for XSCI & XCET Schedule/ BUDGET [kCHF] No. 2019 2020 2021 2022 2023 2024 2025 SUM 1 50 150 265 240 755 2 220 320 590 560 200 1890 3 110 310 4 40 80 15 135 TOTAL (kCHF) 3090 2019 ATS Consolidation Day R. Jones – BE-BI

10 2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019
LHC (1 of 3) No. Activity / Workunit STATUS [EDMS] Description & Consequences 1 Consolidation of LHC Interlock BPM System Active Existing system unable to cover complete dynamic range or cope with doublet bunches. Full vertical slice to be installed during LS2. 2 VME Fan Replacement Missing Currently completing replacement of power supply fans with fan-tray fans foreseen next. 3 Mechanical Spares for Critical LHC Beam Instrumentation Construction of spare parts for operationally critical BI. Presented & approved at LMC. (Wirescanners, Dump BTV & special flanges). 4 Consolidation of LHC Wirescanner Electronics Replacement of ageing electronics to improve reliability during operation. 5 Consolidation of LHC Wirescanner Mechanics New Request to HL cut in first budget review. Current, old LEP mechanics not viable for HL era. Schedule/ BUDGET [kCHF] No. 2019 2020 2021 2022 2023 2024 2025 SUM 1 100 109 209 2 96 296 3 50 150 4 79 129 5 250 180 680 2019 ATS Consolidation Day R. Jones – BE-BI

11 2019 ATS Consolidation Day R. Jones – BE-BI 22.05.2019
LHC (2 of 3) No. Activity / Workunit STATUS [EDMS] Description & Consequences 6 Consolidation of Radiation Hard BLM front-ends Active Missing Addresses noise on long cables. Only development costs paid by CONS. Production paid by HL-LHC. 7 Consolidation of Standard LHC BLM System Replacement of surface electronics to address reliability issues with current digital aquisition system. A vertical slice will be in place for end LS2. 8 LHC Spares: BLM Ionisation Chamber Spares New XX spare ionisation chambers required for LHC. Proposed to be funded through in-kind Russian contribution as part of HL request along with same type to be procured for SPS. 9 Consolidation of Standard LHC BLM System Tunnel front-end Electronics BLM tunnel electronics to be replaced during LS4. Will profit from SPS development and production. Budget for initial development and procurement of special components required before LS3 Schedule/ BUDGET [kCHF] No. 2019 2020 2021 2022 2023 2024 2025 >2025 SUM 6 50 100 150 7 380 27  607 8 9 2019 ATS Consolidation Day R. Jones – BE-BI

12 Description & Consequences Consolidation of Standard LHC BPM System
LHC (3 of 3) No. Activity / Workunit STATUS [EDMS] Description & Consequences 10 Consolidation of Standard LHC BPM System Active Needs complete renovation of all electronics to maintain reliability for HL-LHC era. Assume that fibre-optic cabling is re-used. 2.275MCHF from R2E R2E pays for development of radiation tolerant tunnel components & EP fellows developing single mode fibre transmission system. R2E fellow foreseen for production of these components recently cut – but essential to the project! CONS pay for the production, non-radiation tolerant electronic components, crates & infrastructure Schedule/ BUDGET [kCHF] No. 2019 2020 2021 2022 2023 2024 2025 SUM 10 100 150 200 500 1000 1500 759 4209 2019 ATS Consolidation Day R. Jones – BE-BI

13 Summary of New Requests
Priority Budget (kCHF) Consequence if not done Ionisation Chamber replacement 1 1100+LHC Essential for SPS, TL CONS & LHC Spares. Reduced reliability of BLM system if not done. Hoping for in-kind contribution from Russia. Replacement of Analogue Cameras Production of current cameras being phased out. Majority need replacing by digital cameras by LS3 LHC Wirescanner Mechanics 680 Essential calibration tool for beam size in LHC. Consequence would be further degradation of accuracy & reproducibility. LHC BLM System Tunnel Electronics End of life foreseen by LS4. Consequence would be loss of availability of LHC BLM system. North Area Primary Lines 1/2/3 1148 Priorities & consequences being addressed by BI-EA Working Group North Area Secondary Lines 3090 TT2/TT10 BPM Electronics 2 350 Maintenance problematic. No spares beyond LS3. TI2/TI8 BLMs 630 Reduced availability. Maintenance difficult beyond LS3. SPS Ionisation Profile Monitor 360 Reduced performance & higher maintenance costs 2019 ATS Consolidation Day R. Jones – BE-BI

14 Open Points Production of Spare Ionisation Chambers
Not originally planned to exchange for SPS, but delay from LS2 to LS3 with recent issues & few spares means this should be reconsidered Also required for transfer lines & LHC spares Has been targeted for Russian (IHEP) in-kind delivery through HL-LHC Awaiting outcome of decision North Area Consolidation Huge effort by BE-BI, EN-EA & TE-ABT to define the needs for consolidation throughout the North Area and its primary lines BI-EA working group set-up to agree on scope & define priorities Input now provided to North Area consolidation project with BI needs Priorities still to be clearly defined Consolidation of the LHC BPM System Need to ensure finance for R2E fellow to complete the production and test of up to 10,000 laser transmitter/receivers. 2019 ATS Consolidation Day R. Jones – BE-BI