DGS 412-55 Renovation of Electrical and Communications Systems
This project involves the renovation of all underground power lines and their feeders leading to more redundancy and power reliability. The project vastly improves IT bandwidth, and also allows for the use of VoIP technology for the University phone system.
2
13 FEB 18 6 APR 18 30 JAN 18 15 MAR 18 12 JUN 18 10 AUG 18 10 AUG 18
Trenching near Fairchild field 6 APR 18 DGS project sign near Steam Plant on Prince Street 30 JAN 18 First trench 15 MAR 18 Trenching near Kriner Hall 12 JUN 18 Roadway construction at intersection of Lancaster Drive and Cumberland Drive 10 AUG 18 Original transformers prior to demolition 10 AUG 18 Duct bank construction near Harley Hall 9 MAY 18 Trenching near ROC
3
21 JUN 19 Temporary generator to support campus during planned power outage 21 JUN 19 Final connections of campus electrical network 29 MAR 19 Transformer construction 21 JUN 19 New transformer installation 21 JUN 19 PENELEC tying in