LINAC 3 Meeting ICL machines Injectors

Similar presentations


Presentation on theme: "LINAC 3 Meeting ICL machines Injectors"— Presentation transcript:

1 LINAC 3 Meeting ICL machines Injectors
EN-CV 17 April 2019

2 Summary Reasons for HVAC consolidation Available drawings New ductwork
Main ductwork changes Main building modifications Meeting ICL machines Injectors - 17/04/2019

3 Linac3 - Reasons for HVAC consolidation
Ref. ECR L3-U-EC-0001 (EDMS ) Reasons for ventilation consolidation: The increase of the equipment dissipated heat loads; The obsolescence of existing ventilation units and related components; Ventilation and smoke extraction functions not separated; Reasons for new technical room (IPR approved in September 2018) : Reduced available height of existing room, not compatible with the increase of the flow rate and with the installation of standard dimensions air handling units; Reduced admissible load, not compatible with heavier air handling units; Presence of asbestos in the sealing of joints of the slabs; Lack of water tightness. Meeting ICL machines Injectors - 17/04/2019

4 Linac3 - Available drawings
Existing ductwork: no 3D model available, 2D drawing on CDD CV ver. AA, dated 05/08/1992 (EDMS ) Meeting ICL machines Injectors - 17/04/2019

5 Linac3 - Available drawings
3D models used for integration of new ductwork: ST _01 HVAC 3D model ST _01 Building Linac3 modified by CV Meeting ICL machines Injectors - 17/04/2019

6 Linac3 - New ductwork Due to space constraints and lack of passages, new ductwork is installed in the same volume occupied by the existing one; Horizontal distribution: Ceiling mounted in tunnel and hall zones (no interference with overhead crane) Ceiling mounted in triangle zone; Vertical distribution: existing vertical niches; No return ducts will be installed: existing technical room will become a return plenum; Meeting ICL machines Injectors - 17/04/2019

7 Linac3 - Main ductwork changes
At underground of triangle zone: one air outlet grill to be re-displaced (now hidden behind the stairs) Meeting ICL machines Injectors - 17/04/2019

8 Linac3 - Main ductwork changes
At underground of triangle zone: provisional distribution will be kept (3D model to be updated) Meeting ICL machines Injectors - 17/04/2019

9 Linac3 - Main building modifications
Two new openings on the ceiling of triangle zone for return air (no interference with Linac3 equipment): Meeting ICL machines Injectors - 17/04/2019

10 Linac3 - Main building modifications
Six new openings on the roof (ceiling of existing technical room, no interference with Linac3 equipment): four for static outlets (free cooling mode), two for smoke extractors Meeting ICL machines Injectors - 17/04/2019

11 Linac3 - Main building modifications
New opening on the outdoor wall for connection to the new technical room (ducts, pipes, cable carriers): Meeting ICL machines Injectors - 17/04/2019

12 THANKS