Presentation is loading. Please wait.

Presentation is loading. Please wait.

Ethiopia Operational Hub (ETOH)

Similar presentations


Presentation on theme: "Ethiopia Operational Hub (ETOH)"— Presentation transcript:

1 Ethiopia Operational Hub (ETOH)
Request for Proposal for Investigation and design of Road Structures and water harvesting structures in West Darfur, Central Darfur, North Darfur, East Darfur and south Darfur. RFP :UNOPS/SDN/ /Services /RFP—080 Title: Pre Bid Clearance

2

3 Agenda Attendees registration
Introduction and welcome notes Procurement Manager Purpose of the pre-bid meeting Procurement manager Important dates and duration of works Procurement Manager Contents of the bidding document Procurement manager Conditions of contract (Performance bond, LD) Procurement Manager Scope of the work Project Manager Locations of Road Structures Project Manager New format of BOQ Project Manager Specification Project Manager Support Staff Senior Engineer Questions

4 Qatari Road Structure Project
Objective: Rehabilitate and upgrade existing roads network through spot improvement (crossing points rehabilitation or construction) Means rural roads to be improved have year-round humanitarian access to vulnerable groups and returnees in Darfur through rehabilitation of crossing points and construction of culverts (small Structures) where needed on feeder roads to returnee sites. This Contract cover three structures in South Darfur

5 Scope of work Construct three structures in three locations of East Darfur Coordination of sites are Site 1 Nyala -Al Ryad road, Al Rayd Wadi GPS mE m N Six Cell (2.5X5M) Frame Culvert Site 2 Nyala Thulashi Road, Wadi Skali GPS mE M N

6 General Conditions Specific Conditions
Meeting with local communities shall be conducted at the vicinity of each location Contractor shall ensure to take care of safety of people at work as well the people at vicinity, Take care of local environment and not to clear unnecessary land Camp site shall be well away from village not to disturb the local population Ensure to engage local labour and material as much as possible, Female participation is encourage Shall clear site upon construction and leave as you began, All disturbed areas shall be covered with top soil and grass Specific Conditions All construction material shall be imported from South Darfur Site are in south and North Nyala Both Sites shall commenced simultaneously and complete together Construction material abundantly available near by There is a element of security with all sites, Your rates shall reflect on these issues. UNOPS will not separately reimburse any cost related to the security New Specifications and BOQs were introduced in this contract Site contacts 1 Mohamed Al Tayeb Senior Eng. Nyala South Darfur 2

7 Deliverable Duration of the contract 12 weeks from the date of exchange Performance bond is 0.3% of contractual value LD is 0.1% a day up to 10% contract value Progress will be closely monitored and the contract will be terminated of the acceptable progress against the plan is not made Payment will be made progressively each month. Contractor shall participate in Progress meeting 1st week every month

8 Specifications We have Seven Specifications now instead one.
Job Specific specification TS 1000 Preliminary and site facilities TS2000 clearing and Earth works TS 3000 Soil/Aggregate for Pavements TS 5000 Miscellaneous Works TS Concrete production TS 7000 Concrete Construction

9 Plus we have new format for BOQ
It contains a common BOQ Three separate BOQs are available easy estimate on request BOQ has new pay items Sign Board Mobilization and demobilization two separate pay items Demobilization is to make the site to the original state Each pay item is related to the measurement and payment clause of respective specification No description of work in the pay-item cell. Look for the description in the specification

10 Questions

11 Skali

12 Sakali

13 Al Ryad

14 Al Ryad


Download ppt "Ethiopia Operational Hub (ETOH)"

Similar presentations


Ads by Google