Presentation is loading. Please wait.

Presentation is loading. Please wait.

Rack installation and local tests for the MEBT Chopper Rack

Similar presentations


Presentation on theme: "Rack installation and local tests for the MEBT Chopper Rack"— Presentation transcript:

1 Rack installation and local tests for the MEBT Chopper Rack
João Paulo Martins Controls System Engineer European Spallation Source ERIC

2 Summary Motivation; MEBT Chopper Control System; MEBT Chopper Rack;
Activity Plan; Next steps;

3 Summary Motivation; MEBT Chopper Control System; MEBT Chopper Rack;
Activity Plan; Next steps;

4 Motivation MEBT Fast Chopper was the first MEBT system to be tested in Bilbao; It is the best candidate for this first installation campaign: Familiarization with the environment and the team involved; Required paperwork; Time constraints; One rack for the entire control system, no inter-rack interfaces;

5 Summary Motivation; MEBT Chopper Control System; MEBT Chopper Rack;
Activity Plan; Next steps;

6 Summary Motivation; MEBT Chopper Control System; MEBT Chopper Rack;
Activity Plan; Next steps;

7 MEBT Chopper Control System
FEB Tunnel Timing Events MicroTCA Crate MicroTCA CPU MicroTCA Event Receiver Fine delay Digital out MEBT Fast Chopper Pulser PS Pulser PS 50 Ω 50 Ω Local Protection PLC Temperature sensors, cooling water sensors

8 Summary Motivation; MEBT Chopper Control System; MEBT Chopper Rack;
Activity Plan; Next steps;

9 Summary Motivation; MEBT Chopper Control System; MEBT Chopper Rack;
Activity Plan; Next steps;

10 MEBT Chopper Rack Component Naming Service 19” rack
FEB-040Row:CnPw-U-001 Network patch panel FEB-040Row:NetW-CPP-0101 PLC MEBT-010:Ctrl-PLC-012 MicroTCA crate MEBT-010:Ctrl-MTCA-001 MicroTCA CPU MEBT-010:Ctrl-CPU-001 MicroTCA EVR MEBT-010:TS-EVR-001 Serial to Ethernet converter MEBT-010:Ctrl-SEC-001 / 002 Fiber optics converter MEBT-010:Ctrl-MediaC-001 / 002 Pulser Power Supply MEBT-010:PwrC-PSChop-001N / 001P MEBT Fast Chopper MEBT-010:BMD-Chop-001 MEBT Fast Chopper Loads MEBT-010:BMD-ChopLd-001 / 002 MEBT Chopper Dump MEBT-010:BMD-ChDump-001

11 MEBT Chopper Rack Related documents
Power Distribution Unit: Modified version of the PDU that will be installed on the Magnets racks; Chess document: ESS (for reference) Rack power requirements: Up to 5 kW; Chess document: ESS Rack cooling requirements: 1.16 kW, temperature within 25º C +/- 1º C; Chess document: ESS Rack type: Requirement baseline Rack type U (ESS ); Chess document: ESS

12 Electrical drawings and cable database
MEBT Chopper Rack Electrical drawings and cable database PDU: Under development, to be released this week; Electrical drawings: Under development by WP3 team, based on the connection diagrams provided by ESS Bilbao; Will be necessary for the quality inspection; Internal cables: Needs to be added to Cable Database for proper labelling and identification; Long-run cables: Already in Cable Database and to be procured by the infrastructure team;

13 Summary Motivation; MEBT Chopper Control System; MEBT Chopper Rack;
Activity Plan; Next steps;

14 Summary Motivation; MEBT Chopper Control System; MEBT Chopper Rack;
Activity Plan; Next steps;

15 Activity Plan Pre-installation activities: to be concluded before week 25; Electrical drawings and connection diagrams; Assembly and installation of the PDU; Preparation of MicroTCA crate, including software installation; Naming Service and CSEntry registration; Virtual Machine creation for the PLC IOC; Collection of remaining parts (power cords, network cables, etc..)

16 Activity Plan Rack installation plan: week 25
Reception of the ESS Bilbao rack with mounted equipment; Transport of ESS Bilbao rack to Front-end Building; Removal of the equipment from the “old” rack to the final one in FEB; Connection of MicroTCA and PLC cables; Connection to the Pulsers; Internal verification; Electrical Safety and Quality Inspection; Power up;

17 Activity Plan Local tests activities: week 26
EPICS IOC for PLC: run the IOC on the Virtual Machine and check PVs status; Local test of PLC signals: exercise some inputs on the PLC and verify response on EPICS IOC; EPICS IOC for the Pulsers: run the IOC on the MicroTCA CPU and check PVs status; Using the EVR in standalone mode (14 Hz events) check the fine delay outputs using oscilloscope; Check the availability of the serial communication from MicroTCA CPU to the Pulsers; Exercise some static parameters of the Pulsers and check readback value on EPICS; HV output will not be tested, equipment will remain in “DISABLED” state;

18 Summary Motivation; MEBT Chopper Control System; MEBT Chopper Rack;
Activity Plan; Next steps;

19 Summary Motivation; MEBT Chopper Control System; MEBT Chopper Rack;
Activity Plan; Next steps;

20 Next steps Preparation for the integrated tests;
Replacement of the serial converters to MOXA units; Version 2 of the EPICS IOC wits standard EPICS modules (iocStats, caputlog, recsync); Development of final Control Room interfaces (OPIs); MEBT Chopper diagnostics: reading the voltage signals applied to the loads; Integration with Machine Protection System and the FBIS (Fast Beam Interlock System); Assessment of the MEBT Chopper rack installation; Preparation and execution of a second campaign of rack installations;

21 MEBT Steerers Power Supplies
We will receive 20 of the 22 FAST PS units; In principle they can be placed in the final racks, for storage; ESS is purchasing support bars for all these units, since manufacturer recommends it; This activity will be carried out if the support bars arrive in time and if there will be available time after the local tests of the Chopper rack;

22 Acknowledgement and questions
MUITO OBRIGADO! ESKERRIK ASKO!


Download ppt "Rack installation and local tests for the MEBT Chopper Rack"

Similar presentations


Ads by Google