1 East Hall under construction - 1962
East Area Renovation: Project Team meeting #29 Feedbacks from the worksites and coordination meetings Aboubakr Ebn Rahmoun / EN-EA, East Area Renovation

2 Activities overview Power converter b.251 PS Extraction, F61 b.352
East Hall b.157 A. Ebn Rahmoun, Project Team #29

3 General information Power converter b.251 PS extraction b.352 b.157
Asbestos removal under the old selector ongoing PS extraction b.352 The galleries contain asbestos, some part of de-cabling campaign affected b.157 Emergency evacuation plan during renovation, with help of Louis-Frederic A.  signalisation do be installed Fence installation on south platform ongoing From 1 to 5 July no access via door next to CLOUD Damages during roof renovation & bad weather during June On the control rooms of IRRAD and CHARM Beam line T08b, all equipments and electrical services are consigned Ongoing preparation of an event… A. Ebn Rahmoun, Project Team #29

4 The summer is here So… Doodle East Area Renovation
A. Ebn Rahmoun, Project Team #29

5 Summary Last coordination meeting 26th June, Indico: 830256 B.157
Dismantling (primary area) Buffer area is ready for the dismantling Test & validation of WDP for each operation (T11) ✅ Cleaning of area & handling TCX Storage and Floor load validation on pending from HSE Q100 on CLOUD will be removed soon Survey between T08B and T09-T10 experiments area done EN-CV, dismantling on going, manifolds and water pipes Civil engineering On south wall, dismantling of scaffolding done. The roof refurbishment on going, the dismantling of “lanterneau” started B.352, PS –F61 Magnets dismantling Last magnets have been removed and stored in Prevessin b.954 M100 15t & M200 30t Transport activities, EN-HE Trenches will be opened for removing the hoses removal, TE-MSC/EN-EL EN-CV dismantling on going, manifolds and water pipes 251 & 817 Next steep, EN-EL (+ build.251&157) Buffer area CLOUD Area preparation run *CLOUD run From 02/09 to 15/11/2019 A. Ebn Rahmoun, Project Team #29

6 Status power converters building
On going asbestos removal, to prepare remaining de-cabling @251, obsolete signal, all interlock and the transformer cables. Dismantling false floor pending the de-cabling campaign Inspection by HSE (asbestos) and VIC done to start the de-cabling phase. A. Ebn Rahmoun, Project Team #29

7 PS extraction, F61 Inventaire partie 352 Démantèlement F61
Déconnexions câbles DC & flexibles ED, TE-MSC, Déconnexions du vide et enlèvement pompe à vide, TE-VSC/EN-EA Préparation network, EN-SMM, du 13 au 15/03 Désinstallation BE-BI, LSD, SEC, BTV’s, TFA, BE-BI/EN-HE, TREC et évacuation, matériel stockage, déchets en cours Démontage de la porte secteur, EN-ACE, BE/ICS, Manutention EN-HE Etude structurel du sol validé par SMB, Démontage blindage (coté accès et splitter), évacuation blocs < , Test de charge du pont validé Désinstallation aimants/équipements et supports F61: Lancement VIC TE-MSC, EN-STI => EN-ACE Q74 done TE-VSC, MNPA 25, Q120, MEA (DVT1), MEA (DVT2), QFL, Q600, SMH01(SPLITER) Beam-stopper 01 et 02, EN-STI Démontage blindage MCB, Dump F61D MCB, Q120, Q120, MNPA25, M105, blind access for MCB transport M100 M200, démontage prévu fin Mai, blind access, pont 25t->30t EN-CV dismantling manifolds and water pipes b.352 done, 817->352 on going EN-SMM laser scan + measure on PS magnets EN-EA Shielding relocation between (intersection opening) EN-EL de-cabling DC & signal cable from 251 to 352 Analysis of asbestos risk on galleries from PS, EN-ACE & EN-EA opening trench by EN-HE and hoses removal by TE-MSC A. Ebn Rahmoun, Project Team #29

8 East hall TCX assembly Primary are dismantling Future TCX plug-in
Vacuum disconnected Partial removal T11, magnets BHZ01&02, collimators & beam-stoppers T09,magnets QDE01, QFO02 & BZH01 Magnets removed to reduce the ambient dose rate All instrumentations and the target have been removed TCX (Collimator for primary targets) Highly radioactive and most of them (80%) contaminated, different at each layer: Up to 5 mSv/h contact 70 to 1400 Bq/cm² (up to 500 x CS limit for Co-60 = 3 Bq/cm²) Contamination well managed during intervention: RAS on the floor after intervention < 0.4 Bq/cm2 Very old equipment and little information about configuration Many different parts and composition, (concrete, iron, lead, no controlled ventilation) Future TCX plug-in Estimation Work Dose Planning 0.5 day, 3 pers. handling and decontamination cleaning + 1 Rp agent 218 person.µSv 98 µSv max. indiv Real intervention 1.5 days, 6 pers. handling and decontamination cleaning + 1 Rp agent 434 person.µSv – well optimized compared to the actual duration 99 µSv max. indiv New DIMR version needed (ongoing) *Courtesy to G. Dumont, B. Lopez & J-F Gruber, HSE-RP A. Ebn Rahmoun, Project Team #29

9 Primary area A. Ebn Rahmoun, Project Team #29

10 EAR Schedule A. Ebn Rahmoun, Project Team #29

11 Questions? East Area Renovation A. Ebn Rahmoun, 28-06-2019
Project Team #29