East Area Renovation - Magnets: status June 2019- Roberto Lopez & Jaime Renedo Anglada 28 June 2019
2
SAME 15 existing quadrupoles (QFS, QDS, QFL)
Magnet renovation shared with TT2 magnets Type Quantity Completed Scheduled QFS 8+1 - QFL 3+1 QDS 4+1 3+2 in Magn. Meas. 2019 SAME
3
Four new quadrupole designs
Type Quantity Status Scheduled Q74 L 1+1 Yoke under construction at (CERN) Coils ongoing (ANTEC) 3rd quarter 2019 Q120 C 5+1 First magnet delivered to CERN this week For magnetic geometrical measurement ONLY Q100 L Q200 L 5 Visit to TESLA May. 1st Q100 should be finished by middle of July and 1st Q200 by end of July. 1st quarter 2020 SAME
4
Two new bending designs
Type Quantity Status Scheduled M100 L M200 L Assembly 2 6 8 Both M100 have been accepted 3 M200 have been accepted, 3 are ongoing 4 by CERN and 4 by Nortemecanica 4th quarter 2019 2nd quarter 2020 MCB 7+1 5 finished, 2 ongoing 3rd quarter 2019 SAME
5
12 dipole correctors: half to be built, half to be converted into laminated units
Type Quantity Status Scheduled CR200 4+1 First magnet delivered to CERN. Electrical tests ok but not mechanical. Magnet will be sent back to CNE today 4th quarter 2019 MDX L 8+1 1st yoke delivered to CERN, as the CR200 it will be sent back. CERN coils ready
6
Magnetic measurements: status
All magnetic measurement requests done and accepted Planning of the activities and assignation of the available resources has been done Ongoing activities Dynamic measurements of the QDS: estimation of the delay of the field with respect to the current MCB double powering test (dynamic response): converters are in place and the magnet transport request done
7
Dismantling
8
CR200
9
MDX L yoke
10
M100 L Actual massive New laminated