MQXF-11T Integrated Schedule

Similar presentations


Presentation on theme: "MQXF-11T Integrated Schedule"— Presentation transcript:

1 MQXF-11T Integrated Schedule
A. Grande MQXF CERN Technical Meeting 8th May 2019 CERN

2 Index Structure of the planning Planning overview
Series production of the 11T Models, both MQXF and 11T MQXFBT Prototype Summary table Next steps Antonio GRANDE

3 Structure of the planning
The objective is to merge the previous plannings to have a clear overview of the tasks related with the production and the testing of the different magnets: Series production of the 11T Models, both MQXF and 11T MQXFBT prototype Resources will be taken into account while planning to avoid over-allocation of them  This can impact significantly the planning ! DRAFT Antonio GRANDE

4 Planning overview – Series production of 11T
The 11T production planning is being simplified to a “resource level” For the first study of the MQXFBT prototype’s cold mass, the simplified planning of F. Savary has been taken into account and Cold mass assembly activities have been split into 7 steps DRAFT Antonio GRANDE

5 Planning overview – Models
DRAFT Typical production sequence Typical assembly sequence Typical testing sequence In yellow: testing duration depends on tests performed (to be verified) In green: sequence verified in meetings Antonio GRANDE

6 Planning overview – MQXFBT Prototype
The welding press would be the bottleneck A slot of ~4w is necessary An extra week would be needed to align the cradle for 11T magnets  Delay? ! a DRAFT F. Savary’s planning has been slightly modified to apply the usual duration of a typical Cold Mass Assembly (need verification) In orange: steps in welding press Antonio GRANDE

7 MQXF Prototype Cold mass
Summary table Summary table Magnet Proccess Start date Finish date Comments SP107 Fabrication Depends on 180s activities starting Cold Testing (SM18) SP108  Depends on material availability DP201 MQXFS6 MQXF Prototype Cold mass ( ) Option b SP109 MQXFS4 Antonio GRANDE

8 Next steps Simplification of the 11T series production planning. The minimum level should be the “resource level” Meetings to verify the duration and starting of all the activities Introduce all the resources in every task Antonio GRANDE

9 Thank you