Download presentation
Presentation is loading. Please wait.
1
AD Electron Cooler Consolidation Review
3
Agenda: Welcome and Review charges Speaker: Mike Lamont (CERN)
09:45 → 10:15 History, design and spares of the current AD cooler ( discussion) Speaker: Gerard Alain Tranquille (CERN) 10:15 → 10:45 AD & e-cooling – operational experience ( discussion) Speaker: Tommy Eriksson (CERN) 10:45 → 11:00 coffee break 15m 11:00 → 11:30 The collector issues in 2018 The collector issues in 2018 & general spares situation ( discussion) Speaker: Lars Varming Joergensen (CERN) 11:30 → 12:00 Collector repairs in 2018 & mechanical considerations for the future ( discussion) Speaker: Federico Carra (CERN) 12:00 → 12:30 New collector design and planning for manufacture & installation ( discussion) Speaker: Gerard Alain Tranquille (CERN) 12:30 → 14:00 Lunch 1h 30m 14:00 → 14:30 Optics layout and specifications for the new electron cooler ( discussion) Speakers: Pavel Belochitskii (CERN), Tommy Eriksson (CERN) 14:30 → 15:00 Design of the new AD cooler ( discussion) Speaker: Lars Varming Joergensen (CERN) 15:00 → 15:30 Group contributions, planning and budget for the new AD cooler ( discussion) Speaker: Gerard Alain Tranquille (CERN) 15:30 → 15:45 Coffee 15m 15:45 → 16:30 Closed session
4
Electron Cooling Hardware
Beam dump: collector Source: cathode Vacuum, diagnostics Acceleration system: electron gun Beam transport: solenoids, steering magnets
5
Initial Cooling Experiment (1977-1980)
Low Energy Antiproton Ring ( ) Antiproton Decelerator (2000……) Present cooler is 40 years old : Biggest modifications/upgrades made for LEAR : Upgrade of vacuum system Renovation of power supplies New electron beam collector New electron gun
7
SPARES Electron gun Spare unit and cathodes available. Collector Spare unit has been repaired. New collector construction. Magnets: gun sol toroid drift sol Used on test stand. Power connections to be modified. col sol Vacuum system Complicated toroid chamber Power supplies Responsibility of TE/EPC. Principle cause of concern is the lack of spare magnets. More than one year stop in case of magnet problem (e.g. short circuit) Any vacuum intervention takes a long time because accessibility and bake-out.
8
Parameters for the new AD Electron Cooler
Maximum energy: 80 keV Magnetic field in drift: 600 G Electron beam energy: keV Expansion factor: 2 Antiproton beam momentum: 500 MeV/c Beam radius in drift: 2.5 cm Accelerating voltage: kV Ne x 1013 m-3 Relativistic beta: Drift solenoid length: 1.5 m Maximum electron current: 3.5 A Cooler orientation: horizontal Cathode radius: cm Vacuum chamber diameter: 140 mm Magnetic field in gun: G
9
What will be different? Cooling at a higher antiproton momentum (≤500 MeV/c) Horizontal orientation Electrostatic plates in each toroid. NEG coated vacuum chambers. Fast ramping of the expansion solenoid to adapt the electron beam size during cooling. New solenoid design using pancakes and iron bars for the return-flux. Compact orbit correctors (as used on ELENA).
10
Cooler more accessible. No need for working at heights.
Vertical orientation (present situation) Horizontal orientation (proposal) 5 x 5cm coils 2cm gap 12 x 1cm iron rods for the return flux 33cm coil 1cm iron shield Fine adjustment of magnetic field possible Only a handful of spare coils will be needed Easier mounting Lighter structure
11
New electron gun design (courtesy of Alexander Pikin)
Collector studies at 65 keV, 3.5 A
12
Advantages of a new Cooler
Present cooler New cooler Gain Max Ee (keV) for cooling 27 68 Corresponding beam momentum (MeV/c) 300 500 Shorter deceleration ramp from 2 GeV/c. Smaller initial emittances. Faster cooling with lower equilibrium emittances. Gun perveance (10E-6 mP) 0.58 2.6 Ie at 100 MeV/c (mA) 105 470 Four times faster cooling at extraction energy. Expansion factor 1 2 Electron beam transverse temperature (meV) 100 25 Four times reduction in electron beam transverse temperature resulting in faster cooling and smaller equilibrium emittances. Bt/Bl 1.00E-03 1.00E-05 Electron beam losses losses 1.00E-04 Better collector efficiency with electrostatic plates in the toroid magnets. Vacuum pressure in cooling section (torr) 2.00E-11 4.00E-12 Pressure reduction with extra pumping from NEG. Less outgassing from secondary beam loss. Less blow-up due to vacuum.
13
Cost Comparison (new cooler vs spare parts)
Total budget : MCHF For new cooler Design, drawings 250 kCHF >4500 hours Magnetic system 1000 kCHF Incl. spare coils Raw materials & production 750 kCHF Vacuum chambers, BPM….. Vacuum 50 kCHF NEG (coating,strips), acceptance tests HT platform 100 kCHF Cabling Misc. 227 kCHF Total budget : MCHF For spare parts New collector 350 kCHF Spare magnetic elements 550 kCHF 1.3m gun & 0.7m collector solenoids, toroid Design, drawings 100 kCHF Spare cathodes, vacuum cons. 165 kCHF Ion pump, NEG cartridges, toroid chamber
14
Timeline (new cooler vs spare parts)
2019: Design of new collector. Produce drawings. Start production. Specification of the magnetic system. Produce tender documents. Market survey (?). Finish integration study (incl. magnets reshuffle). Finalise gun study and design. 2020: Call for tender for the magnetic system. Production of the new collector (ready for autumn). Produce drawings for the electron gun. Start production (?). Design of the vacuum system. Drawings ready for end of year. Test new collector on ecool test stand. 2021: Install new collector on AD. Exchange electron gun. Ready for start-up. Magnets production. Production of the vacuum system. Chamber coating. Vacuum acceptance tests. 2022: Continue production and acceptance tests/measurements of magnets and vacuum system. Mounting in bld 236 (ecool test stand). 2023: First tests of the new cooler. LS3: Consolidate vacuum system.
15
Review Conclusions A preliminary proposal for the construction of a new e-cooler was presented. The new e-cooler will not ready for installation before end 2023 at the earliest, leaving potential operation in presently schedule Run 3 of 1 year. A re-designed collector is in the design stage. Tight schedule for installation in LS2. AD will be continued to be exposed to risk of gun, collector solenoids, toroids in Run 3. A recommendation on this requires a risk benefit analysis, which requires further input from BE-BI. Spare magnetic elements would cost of order 700 kCHF, these plus new collector and other measures would guarantee life of AD e-cooler but without listed benefits of new system. In any case these additional spare components will not be available much earlier than a new e-cooler and can therefore not really be considered as a risk mitigation measure. The review panel think it needs to be justified why spare parts are not possible in a shorter time frame. A recommendation on this requires a risk benefit analysis, which requires this input from BE-BI. Present degraded operation not understood. Choice appears to be between: new e-cooler with benefits, but costly (material, labour) and only realistically available after LS3; and production of spares and other consolidation allowing continued operations until end of life.
16
Summary of recommendations
At the present time it is not possible to give a clear recommendation on building a new cooler. We propose the following set recommendations in order to reach a conclusion. For End June 2019 1. Produce an alternative scenario for spares (starting from what is already received). 2. Discussion with TE-MSC about responsibility for magnet design and production (both scenarios) 3. Of the possibilities mentioned at the review (present spares, spares for a new cooler, layout changes, changes to power converters if needed) – clarify which are in the consolidation request. 4. Assessment if optics improvements, and the layout configuration, can be made independently of the new cooler – and budget and timeline estimate. Assessment if the gun improvements (to 4 times higher perveance) are alone sufficient faster cooling, and could this be implemented on the existing cooler. These questions are presently being addressed
17
Follow up on recommendations from reviewers (questions to be finally answered by the end of June 2019): 1. Produce an alternative scenario for spares (starting from what is already received). • New collector is common to both present and new e-cooler design. • Drawings of present magnets nor available. Reverse engineering would take as long as a new design. Even if drawings found, EN-MME should be involved to make production drawings and tender documents. A complete magnetic system would be available by end of 2022. 2. Discussion with TE-MSC about responsibility for magnet design and production (both scenarios) • Davide Tommasini is available for collaboration at any level of involvement desired by BE-BI. • The collaboration between TE-MCS and BE-BI should be well specified from the beginning. ACTION BE-BI: meeting with TE-MCS to draw terms of collaboration. 3. Of the possibilities mentioned at the review (present spares, spares for a new e-cooler, layout changes, changes to power converters if needed) – clarify which are in the consolidation request. Pin down what is actually included in the budget request, as it was not well understood by the panel: • Power Converters for HV already included. Note, one 80kV already ordered to use on the test stand. • Power Converters for Magnets NOT included. Note that all magnets are in series and bending angle does not scale with energy. Present PC could be used for the new e-cooler. ACTION BE-BI: enquire with TE-EPC if present PC (which are dated) should be replaced. • Spares included for the new e-cooler: 1 gun, 1 collector, 1 coil for the pancake structure. • E-Cooler instrumentation consolidation NOT included in the option of present spares. • Layout changes NOT included. 4. Assessment if optics improvements, and the layout configuration, can be made independently of the new e-cooler – and budget and timeline estimate. • Layout changes are independent of whether we go for spares of the present e-cooler or installation of the new e-cooler. The idea presented was to re-shuffle the magnets at the same time as the new e-cooler installation, profiting from the big intervention. Vice versa, the new e-cooler design does not depend on the layout changes, only its performance (improved). • ACTION BE-OP (Laurette Ponce), EN-EA (Francois Butin) and BE-ABP (Davide Gamba): follow up on layout changes. 5. Assessment if the gun improvements (to 4 times higher perveance) are alone sufficient faster cooling, and could this be implemented on the existing e-cooler. • It is feasible to design a new gun with 4 times higher perveance, working possibly at higher HV.
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.