Presentation is loading. Please wait.

Presentation is loading. Please wait.

Minuteman Vocational Technical Regional High School Progress

Similar presentations


Presentation on theme: "Minuteman Vocational Technical Regional High School Progress"— Presentation transcript:

1 Minuteman Vocational Technical Regional High School Progress
May 20th 2019 – June 17th 2019

2 June 17th View of Area A+B – Upper Level
Bathroom finishes substantially complete; toilet partitions, accessories and fixtures. June 17th View of Area A+B – Lower Level Flooring materials substantially complete. Testing and Balancing of Mechanical Equip in progress.

3 June 17th View of Area G – Exterior
Both Greenhouses in progress with exterior wall and roof glass installation.

4 June 17th View of Area D – Upper Level
Typical classroom on floor substantially complete June 17th View of Area D – Lower Level Ceramic wall tile substantially complete. Ceiling grid in progress, MEP devices to follow.

5 June 17th View of Area D – Gymnasium
Wood Gym floor court lines and logos complete. Final coats of sealer in progress, vented base installation to commence Wednesday.

6 June 17th View of Area E – Upper Level
Skylight openings complete and painted. June 17th View of Area E – Upper Level Ceiling tile installation in Media Center complete. VCT Flooring in classrooms & offices complete.

7 June 17th View of Area E+F – Cafeteria
Painting substantially complete. Ceiling tile installation in progress. Ceramic wall tile in progress

8 June 17th View of Area F – Lower Level
Millwork installation in progress. Plumbing fixtures installation in progress. Epoxy floor in Kitchen complete. Setting of Kitchen Equipment in progress.

9 June 17th View of Area C – Theater
Installation of fire curtain system complete. Counterweight rigging system in progress. June 17th View of Area C – Band & Chorus Millwork & Casework installation complete. VCT Flooring installation in progress.

10 June 17th View of Area A+B – West Roadway
Loam and seed of drainage swale complete. Perimeter roadway asphalt binder complete.

11 June 17th View of Faculty Parking Lot - South
Asphalt binder complete. Setting of curb & concrete sidewalk placement in progress.

12 June 17th View of Faculty Parking Lot–North
Asphalt binder complete. Setting of curb & concrete sidewalk placement in progress.

13 June Construction Schedule Look Ahead:
Area A+B & G Complete Testing & Balancing of Mechanical Units – Area A+B Remain, Area G completed as of this update Complete Concrete Sealant of Shop Floors Continue Punchlist Process Area D Complete floor finish on Gymnasium floor Commence Wall Pad, Bleachers and Scoreboard installation Commence Testing & Balancing of Mechanical Units. Unit feeding the Gymnasium previously completed Commence Punchlist process Area E Complete Classroom/Office Flooring Installation on Lower Level Complete Millwork installation in Media Center and Lower Level Commence Corridor flooring Installation on Upper & Lower Level Area F Complete Installation of Ceramic Wall Tile Complete with installation of Millwork Continue with installation & connections of Kitchen equipment Area C Complete Mechanical Hoist Rigging Installation Complete Flooring activities in Band & Chorus Area Continue Counterweight & Guidewall Rigging Installation Commence Testing & Balancing of Mechanical Unit that feeds Band & Chorus Exterior/Sitework Continue installation of granite curbing in faculty parking lot Continue with placing concrete sidewalks and speed tables Continue with landscaping plantings at perimeter of site Continue with fill & utility installation in the Student parking lot

14 Project Turn-Over Schedule Look Ahead:
Activities Start End New Furniture Delivery 7/8 7/26 Temp Certificate of Occupancy 7/25 Building Construction Punch List 9/24 Mover moves Administration 7/29 7/30 Administration Staff in New School 8/5 Mover moves Shops & Classrooms: 8/15 Mover moves Summer Edge 8/19 Managers/Leads Return 8/26 8/28 ALL STAFF ORIENTATION 8/29 Teachers Meeting & Student Orientations 9/3 9/4 ALL Students first day of school 9/5

15


Download ppt "Minuteman Vocational Technical Regional High School Progress"

Similar presentations


Ads by Google