Progress on cryostat design and production
Fresca 2 cryostat Progress on cryostat design and production A. Vande Craen, 29/05/2019 29/05/2019
2
Update Design and fabrication to be done by EN-MME
Meeting to be planned with different actors of the project to discuss the requirements Kick-off meeting held on 16/05/2019 Work package description in preparation Scope Deliverables Share of responsibilities Planning 29/05/2019
3
Planning New planning in preparation by EN-MME Main milestones
Delivery (pre-assembly tested) for end-2020 Installation finished for March 2021 (TBC) 29/05/2019