ME I&C -- PC Electronics
19-April-05 Status of LV + endcap LV ready for operation ALL of plus end ready to begin operations ME+1 far side being run for pcrate testing DCS panels are run directly on S4F10 DCS computer New procedures posted For cold startup/shutdown For overnight startup/shutdown Next to do Need to install air ducting in ME+(-)1 X2 Maraton racks Remember we are in supervised operation only DSS not final Rack DCS not final Safety review not made 22-Nov-19 ME I&C -- PC Electronics