Download presentation
Presentation is loading. Please wait.
Published byЕвгения Раевская Modified over 5 years ago
1
Senior Design I – Project Review P07008 – ArcWorks Wash Bottle Assembly
Team Members: Sagar Sheth Team Leader Leonardo Silva Industrial Eng. Stephen Bennice Mechanical Eng. Gabriela Jaramillo Mechanical Eng. Eric Van Hemel Mechanical Eng. Robert Veiders Mechanical Eng. Eng.Faculty Guides: Dr. DeBartolo Dr. Marshall
2
P07008 Project Description Automate the process of assembling nozzle to wash bottle Key Customers Needs: Can accommodate different size bottles ( 250 ml, 500 ml, 1lt) Should be able to produce large quantities of assemblies (min life of 120,000 cycles) Should require minimal force to complete assembly (less than 25 lb) Should create good assemblies The unit should not create additional disabilities for the operators Process improvement of wash bottle line
3
Basic Assembly Components Completed Assembly
4
Current Process Assembly Process
5
P07008 Design Concept
6
P07008 Design Concept
7
P07008 Design Concept
8
P07008 Design Concept
9
P07008 Design Concept
10
P07008 Design Concept
11
P07008 Design Concept
12
Current Layout
13
Future Layout
14
Proposed Layout
15
P07008 High Risk Assessment Risk: Main component of assembly is hard to manufacture. Tight tolerances Intricate shape Proposed Mitigation Divide main component into various parts if machining is out of specs.
16
P08907: Current Stage of Product Development
1 Phase 1: Planning 2 Phase 2: Concept Development 3 MSD 1 Phase 3: System Level Design 4 Phase 4: Detailed Design Current Phase of Product Development 5 Phase 5: Assembly, Testing and Refinement MSD 2
17
P07008 Current State of Design
Design meets customer needs and engineering specs 6 cases of different size bottles can be assembled with an expected average cycle time not exceeding 10 seconds No intervention between the operator and the machine while actual assembly Force required to complete assembly by operator is less than the minimal force required (25 lb) to complete assembly manually for a bottle. Actual force will be approximately 2 ounces Better material flow savings in time and distance traveled Budget Review Budget = $ Projected Cost = $ Mitigation of no compliance Better ergonomic manual tool
18
MSD II Project Schedule
Have machine built and tested by early April Have all the documentation completed by mid-April Have process improvements completed by mid-April Complete technical paper and poster by first week of May
19
SD II Schedule
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.