19th July 2019 Finish the MU96 re-installation EN-EL lights renovation (Gallery 3) Asbestos cleaning campaign (MU08 – MU13) LINAC4 connection BTP installation Lighting change over sequence – Phase 1 BTP inst. Lighting and power change over to take place Friday morning to definitive supplies (ME45/Building 365). Lighting will be swapped sequentially to avoid any blackouts within the affected zones of the PS. 50% of normal lighting will be available at all times. EN-EL consolidation SMB asbestos cleaning MU96 re-installation No access to the inner and outer PS galleries No access between SS07 and SS14 LINAC4 connection 4-Jul-2019
2
19th July 2019 EN/EL Lighting + Power change over in PS, SS39-SS76
Friday 19th July Lighting change over sequence – Phase 1 BTP inst. Lighting and power change over to take place Friday morning to definitive supplies (ME45/Building 365). Lighting will be swapped sequentially to avoid any blackouts within the affected zones of the PS. 50% of normal lighting will be available at all times. EN-EL consolidation SMB asbestos cleaning MU96 re-installation No access to the inner and outer PS galleries No access between SS07 and SS14 LINAC4 connection 4-Jul-2019
3
19th July 2019 Finish the MU96 re-installation
EN-EL lights renovation (Gallery 3) Asbestos cleaning campaign (MU08 – MU13) LINAC4 connection BTP installation Lighting change over – Phase 2 BTP inst. EN-EL consolidation SMB asbestos cleaning MU96 re-installation No access to the inner and outer PS galleries No access between SS07 and SS14 LINAC4 connection 4-Jul-2019
4
19th July 2019 Finish the MU96 re-installation
EN-EL lights renovation (Gallery 3) Asbestos cleaning campaign (MU08 – MU13) LINAC4 connection BTP installation Lighting change over – Phase 3 BTP inst. EN-EL consolidation SMB asbestos cleaning MU96 re-installation No access to the inner and outer PS galleries No access between SS07 and SS14 LINAC4 connection 4-Jul-2019
5
19th July 2019 Finish the MU96 re-installation
EN-EL lights renovation (Gallery 3) Asbestos cleaning campaign (MU08 – MU13) LINAC4 connection BTP installation Lighting change over – Phase 4 BTP inst. EN-EL consolidation SMB asbestos cleaning MU96 re-installation No access to the inner and outer PS galleries No access between SS07 and SS14 LINAC4 connection 4-Jul-2019
6
19th July 2019 The power change over will be done in two phases.
Finish the MU96 re-installation EN-EL lights renovation (Gallery 3) Asbestos cleaning campaign (MU08 – MU13) LINAC4 connection BTP installation Power change over – Phase 1 BTP inst. The power change over will be done in two phases. Each area will be inspected to ensure that no works are in progress before the change-over. EN-EL consolidation SMB asbestos cleaning MU96 re-installation No access to the inner and outer PS galleries No access between SS07 and SS14 LINAC4 connection 4-Jul-2019
7
19th July 2019 Finish the MU96 re-installation
EN-EL lights renovation (Gallery 3) Asbestos cleaning campaign (MU08 – MU13) LINAC4 connection BTP installation Power change over – Phase 2 BTP inst. EN-EL consolidation SMB asbestos cleaning MU96 re-installation No access to the inner and outer PS galleries No access between SS07 and SS14 LINAC4 connection 4-Jul-2019