Voice Upgrade Project Initiation Certification Request
Presented by: Sharla Hernandez Chris Moultrie July 25, 2019
2
Project Background Department of Information Technology (DoIT) provides core technology services to State of New Mexico executive agencies One of these core services is traditional voice communications, including: Analog, digital, and voice over internet protocol (VoIP) services Voic Toll and toll-free long-distance services Conference calling and audio conferences Basic unified communications services Basic call center services To deliver service, DoIT operates approximately 20,000 stations using four technology platforms Fujitsu: approximately half the current stations via three hubs Mitel: 300 small telephone systems, of which DoIT manages 80 Cisco: approximately 1055 stations serving eight agencies Avaya: remaining stations
3
Project Purpose ISSUES
Fujitsu system is past end of life (EOL) and end of service (EOS); failure of significant component could result in major outage of indefinite duration Mitel offers minimal feature set and limited integration with current telephone network; lease agreements expires June 2020 and can be extended only on month-to-month basis, making Mitel more difficult and expensive to sustain GOALS To protect State from risk of major voice communication outage, replace Fujitsu platform entirely Migrate to a more consolidated architecture comprising Avaya and Cisco technology to improve cost-effectiveness and maintainability Offer State agencies new voice communication features as a by-product of upgrade
4
Project Timeline
5
Project Funding & Budget
Source Amount Associated restrictions Laws of 2019, SB 280, Section 61 $6,298,715 Fiscal Year to plan, design, purchase, install and implement infrastructure to improve or replace the central telephone system statewide TOTAL deliverable BUDGET Estimate Project charter $0 Project management support, including: Project management plan Risk assessment Certification documents Contract documents $100,000 IV&V $30,000 Wiring Contract (if required) $50,000 Implemented voice technology $6,118,715 total $6,298,715
6
Initiation Phase Activities
Complete and/or verify inventory of voice technology (including locations and customers) to support additional planning Develop guide for agency-by-agency discovery and begin that process Implement project governance structure Initiate project-related communications Plan Independent Verification & Validation (IV&V) approach Develop draft Voice Upgrade Project Management Plan, including initial work plan and implementation strategy Build project team, including obtaining contractor project administration support
7
We request certification for Initiation, with $20,000 in funding for work during this phase
Questions?