General Services Department (GSD) Asset Management (AM) Project Project Certification Committee Implementation Phase Request October 24, 2019 Duffy Rodriguez, GSD Deputy Cabinet Secretary Michael Lujan, GSD Administrative Services Division Director Karen Baltzley, GSD Chief Information Officer John Salazar, PMP
2
ASD Project Abstract Administration Services Division (ASD) is initiating the Asset Management Module Project to replace the legacy software with a proven enterprise software module that has been successfully implemented in other state agencies in order to improve efficiencies and to provide better services to the GSD constituents.
3
GSD Business Need The New Mexico General Service Department (GSD) is currently utilizing SunSystems, a web based, commercial off- the-shelf software (COTS), to manage approximately $820M of capital assets. SunSystems does not provide GSD with the needed tools to manage its assets throughout the procure to pay; record to report; and acquire to retire life cycles. Specific challenges include limited reporting capabilities; lack of an automated audit trail; time consuming manual reconciliation between SunSystems and other systems; and excessive manual data entry. Combined, these challenges result in fixed asset business processes that are error prone, inefficient and not cost effective.
4
GSD AM Project Objectives
Implement the SHARE Asset Management (AM) module that will enable ASD to more effectively manage assets throughout their lifecycle and simplify related maintenance and administrative tasks. Eliminate duplicate manual processes and legacy systems, leading to improvements and eliminating potential data integrity threats caused by human error. Improve business processes for reporting and analysis related to agency balance sheet and net financial position. Satisfy Audit Rule requirement for Financial Statement Generation.
5
Planned Approach This project will utilize the existing PeopleSoft software modules utilized by the State of New Mexico and under the direction of the SHARE Enterprise Resource Planning (ERP) Management Team. GSD has entered into a Professional Service Contract with Deloitte Consulting LLP for the implementation of the SHARE AM module. GSD intends to leverage the existing SHARE enterprise platform and existing computing infrastructure currently operated and maintained by DoIT.
6
Work Performed to Date Deloitte Project Planning Activities - Initiated CSW Project Management Services - Initiated Data Conversion Planning Activities - Initiated Legacy Data Cleansing - In Process Project Kickoff Meeting - Completed Project Teams – Have Been Defined Business Process Flow and Functional Meetings – In Process
7
Activities Planned During the Implementation Phase
Project Management Services Continuation of Business Requirements Gathering Configuration and Software Prototypes #1 and #2 Legacy System Data Conversion Testing Develop Test Plan & Scripts Integration and User Acceptance Testing (UAT) Deployment Configuration Workbook & Deployment Plan Training Materials & Knowledge Transfer Go-Live Support
8
GSD AM Certification History
Approved Certification Date Certification Amount Funding Source: 5/31/2019 $40,000.00 Laws 2019, Chapter 271, Section 7, Item 11 *Emergency Certification 6/27/2019 $82,350.00 Total Certified $122,350.00 This Request Certification Date Certification Amount Funding Source: 10/24/2019 $427,650.00 Laws 2019, Chapter 271, Section 7, Item 11 Total this Request
9
GSD AM Professional Contracts
Contract Number Status (Released, Awarded or In Process Vendor Description Total Value Awarded CSW Enterprises, LLC Project Management Services $39,037.50 Deloitte Consulting, LLP Implementation Vendor $482,000.00 $521,037.50
10
GSD AM Proposed Schedule
October November December January February March Mobilize Architect Process Design & Requirements Configure & Prototype Software Prototypes 1 & 2 Test 2 SIT Cycles, UAT, Conversion Dry Runs Deploy Training and Cutover Go-live Support GSD Data Conversion
11
Status of IV&V GSD submitted a waiver request to DoIT for the IV&V project requirements. The waiver was approved on 7/10/19.
12
GSD Requests PCC Approval
Approval to proceed to the Implementation Phase of the Project Certification funding approval in the amount of $427,650.00
13
GSD Asset Management Project
Questions? Thank You!