1 Global Leader in Load Bank Rentals & Service
Innovations in Data Center Commissioning

2 Load Testing – Not what it used to be
3/25/2017 Innovations in Data Center Commissioning

3 Commissioning Objectives
Validate system design and performance Ensure operational uptime Qualify for LEED certification Document Test Data & Results Competitive Advantage Attract new Data Center clients 3/25/2017 Innovations in Data Center Commissioning

4 Innovations in Data Center Commissioning
What gets tested Back up diesel generators (in parallel) UPS systems Automatic transfer switches Power Distribution Units (PDUs) Computer Room Air Conditioning (CRAC) Hot aisle/cold aisle layout Pods & containers 3/25/2017 Innovations in Data Center Commissioning

5 Innovations in Data Center Commissioning
Why it makes sense Generators, UPS, PDUs CRAC systems, chiller, hot aisle/cold aisle validation, rack layout need to be validated Deficiencies in any of these areas result in project delays or operational downtime Reconfiguring and retesting adds significant costs to data center budgets and results in downtime of production systems to correct 3/25/2017 Innovations in Data Center Commissioning

6 Commissioning – Not always a priority
Perception: We can figure this out when the time comes Reality: Should be part of the planning process Ensure all test specifications are planned for Ensure budget is complete Ensure schedule is met 3/25/2017 Innovations in Data Center Commissioning

7 Paradigm Shift #1: An Integrated Testing Plan???
Plan for commissioning as early as possible Think about commissioning in the design phase Integrate the commissioning plan into the design process Know what you are going to test Develop test specs Ensure all test specifications are planned for and met Ensure budget is accurate & complete Ensure timely execution Ensure design meets energy certification standards 3/25/2017 Innovations in Data Center Commissioning

8 Integrated Commissioning Plan
Review of testing requirements Evaluate equipment in relation to testing objectives Plan for development of customized test solutions Develop REALISTIC budgetary forecasts Plan for equipment training Site walk for equipment placement, access, ingress and egress Logistics 3/25/2017 Innovations in Data Center Commissioning

9 Innovations in Data Center Commissioning
The Value Prove systems prior to production by simulating the operating environment Validate design specs and operational performance Reduce cost and risk of reworking/re-engineering Use test data as a marketing tool to attract tenants 3/25/2017 Innovations in Data Center Commissioning

10 Innovations in Data Center Commissioning
Collaboration Coordinate with client contractors who are invested in commissioning success: General Contractor Electrical Contractor Mechanical Contractor Commissioning Agent Don’t forget the client  3/25/2017 Innovations in Data Center Commissioning

11 Case Study: An Integrated Commissioning Plan
Started planning 1 year before data center construction was completed Reviewed spec – identified challenges Required solution for hot aisle/cold aisle containment – that did not exist ComRent developed a solution to meet the granular testing spec required Solution build took 4 months Delivered project on time, on budget & commissioned to spec Customer was happy! 3/25/2017 Innovations in Data Center Commissioning

12 Case Study: The “Just In Time” Plan
Ordered load banks at the last minute (from another vendor) No site walk Load banks didn’t fit in freight elevator - Delay Set up load banks outside - Delay Cable runs were wrong - Delay It rained – indoor load banks + rain = No Test - Delay Project behind schedule Project over budget Customer not so happy 3/25/2017 Innovations in Data Center Commissioning

13 Paradigm Shift #2 – Use Technology To Reduce Cost
It is not about the cost of equipment rental It is about the total cost to complete commissioning New technology can accelerate schedule and reduce labor costs Medium Voltage Load Banks – require 15x Fewer Cables and 5x less time to set up and tear down – fewer points of failure Wi-Fi Control – reduce time and associated man hours to complete tests Power Quality – New monitors complete more tests in less time, collect more data and reduce report generation time 3/25/2017 Innovations in Data Center Commissioning

14 Innovations in Data Center Commissioning
Generator Testing More medium voltage generators being deployed Makes sense to test with actual medium voltage loads CR922A 5MW MV Load Bank: Transportable medium voltage load bank Does not require a transformer CAPACITY: VAC 4,160 VAC Easy set up – 3 MV cables Linkable for larger loads (50MW) Reduces labor cost 3/25/2017 Innovations in Data Center Commissioning

15 UPS Systems Integration Test
Testing at full load to simulate real world outage Testing at unity or PF (i.e. - .8) or both? Unity – resistive 400kw Load Banks Linkable to meet larger load spec PF – Resistive/Reactive Load Banks Linkable for large loads Resistive Only Test Reactive Only Test Resistive/Reactive Test 3/25/2017 Innovations in Data Center Commissioning

16 Power Distribution Unit(s) (PDU)
Where are you testing? On the raised floor/maintenance room Remote Power Panel (RPP) Overhead bus track Under raised floor track New bus track adapters Faster set up Shorter cable runs It’s just easier 3/25/2017 Innovations in Data Center Commissioning

17 CRAC & Economizer System Testing
DCM Room Validation Test: Balance electrical and chiller loads Ensure Optimum Thermal high load levels Ensure constant temp and pricise humidity levels Measure room air flow Measure room Delta T Test aisle layout = Integrated Systems Test 3/25/2017 Innovations in Data Center Commissioning

18 Hot Aisle/Cold Aisle Containment
Precisely simulate production server loads & airflow: Validate aisle layout (perforated floor) Validate CRAC capacity Variable load Variable CFM Measure Delta T 3/25/2017 Innovations in Data Center Commissioning

19 Container/Pod Testing
Rack mount load banks The only way to validate pod electrical and chiller capacity Tune load banks to simulate actual server configuration Variable load Variable CFM Validate Delta T 3/25/2017 Innovations in Data Center Commissioning

20 Innovations in Data Center Commissioning
Power Quality CX Power Monitor One solution replaces: Drantez™, Astro-Med™ and HoBo™! Very accurate (voltage and current) Simple set-up & automated data capture (programable) Simple report writing Calibrated & tested (every shipment) (Ground) current triggering Symmetrical components/zero sequencing (sums the currents) Data archived after each usage PQ + wireless Temp/Humidity probes (1-100) Wi-Fi, Ethernet & USB interface Free software (Live-View™ & U-View™) & upgrades 3/25/2017 Innovations in Data Center Commissioning

21 Innovations in Data Center Commissioning
What’s Next? Wi-Fi Communications: IP addressable load banks Manage all load banks via a single laptop or Android device At the rack In the aisle In the room Save time Save labor! Customized MS Windows GUI Android Smartphone Interface Application 3/25/2017 Innovations in Data Center Commissioning

22 Innovations in Data Center Commissioning
What’s Next? In Aisle, Water Cooled Load Simulator: 250kw or 500kw configuration Light weight: 250kw unit = ~700lb. 500kw unit = ~1200lb Fully integrated into chilled water loop Continuously variable flow control Continuously variable power (load) control Continuously variable Delta T control 3/25/2017 Innovations in Data Center Commissioning

23 Innovations in Data Center Commissioning
Summary Controllable load solutions have come a long way from the Salt Water Pickle Barrel Solutions designed to meet very specific requirements New Solutions enable more granular data collection Validate Data Center design and operational efficiency Clients have inquiring minds – They want to know! Commissioning is now a Competitive Advantage in a competitive marketplace 3/25/2017 Innovations in Data Center Commissioning

24 Innovations in Data Center Commissioning
Right. Ready. Reliable. 3/25/2017 Innovations in Data Center Commissioning