Palo Alto Road Separation Potential Impacts Planning & Transportation Commission June 17, 2010
2
At Grade Alternative
3
Preliminary Alternatives Analysis p51
4
HSRA Assumptions 8% road grade 22 foot vertical separation if elevation change from existing to future driveway is greater than 2 feet, full parcel acquisition is assumed No road closures (unless requested by the City)
5
CHARLESTON
6
Charleston Road Impact Summary Neighborhoods – Charleston Meadows, Greenmeadow, Fairmeadow Parcel Impacts – 23 Full Parcel Acquisitions (all R-1) – 16 Partial impacts (all R-1) Road depressions – Charleston, Alma, Park and Wright Estimated full parcel acquisition values – $26,087,000
7
MEADOW
8
Meadow Drive Impact Summary Neighborhoods – Charleston Meadows, Ventura, Fairmeadow, Midtown Parcel Impacts – 24 Full Parcel Acquisitions (22 R-1 + 1 RM-30 + 1 CN) – 19 Parcel Impacts (18 R-1 + 1 PC:Alma Plaza) Road depressions – Meadow, Alma, Park, 2 nd and Emerson Estimated full parcel acquisition values – $21,072,000
9
Churchill Ave Underpass CHURCHILL
10
Churchill Ave Impact Summary Neighborhoods – Southgate, Old Palo Alto Parcel Impacts – 36 Full Parcel Acquisitions (13 R-1 + 11 R-2 + 12 RM-15) – 7 Parcel Impacts (5 R-1 +1 RM-15 + 1 School:Paly) Road depressions – Churchill, Alma, Mariposa – minor change to Castilleja, Kellogg & Coleridge Estimated full parcel acquisition values – $50,753,000
11
Totals 83 Full Acquisitions – 58 R-1 + 11 R-2 + 12 RM-15 + 1 RM-30 + 1 CN – Value Estimate of Residential properties only: $97,912,000 42 Parcel Impacts – 39 R-1 + 1 PC (Alma Plaza) + 1 RM-15 + 1 School(Paly)
12
Marked Up Map www.maps.google.com Select search options
13
Palo Alto Right of Way* Peers Park Meadow Charleston San Antonio University Embarcadero Alma Cal Ave 96 ft 85 ft 79 ft *Approximate – not perfectly to scale. Not official diagram.