1
BETTER SOLUTIONS KMS : PRESS Transport/Installation 2006.08.30
2
1. Project Overview 2. Project Execution Schedule 3. Ocean Transportation 4. River Transportation 5. Inland Transportation 6. Site installation and commisioning Contents BETTER SOLUTIONS
3
1.Project Overview Manufacturer & Supplier : Rotem Company / WIA Corporation (Korea) Site : KIA Motors Slovakia (Zilina, Teplicka site) KMS Equipment List ShipmentDescriptionWT(Ton)CBMFOB Date 1 st shipment5,400T Press & Auxiliaries4,0869,1132005.09.30 2 nd shipment5,400T Press2,8146,1042005.12.30 Total6,89015,217 Transport Schedule : Masan Rotterdam/Constanza Rinz Zilina (sea : 25~35d duration) (river : 15d) (land : 10d) Installation/Commissioning : Press #1st + Aux.–05.12~06.01 / 06.01~04 #2nd – 06.03~05 / 06.05~07
4
BETTER SOLUTIONS 2. Project Execution Schedule Schedule 05 year06 year junjulyaugsepoctnovdecjanfebmaraprmayjunjulyaug presentation(6/29) Proposal letter Final quotation contracting Contract (exec.co) final Packing list Transportation(1 st ) Installation/trial(1 st ) Transportation(2 nd ) Installation/trial(2 nd )
5
BETTER SOLUTIONS 3. Detail schedule for ocean transportation shipment (changwon) trucking masan (to load) loading (bulker) Ocean transport (bulker) discharging (rotterdam) barging Barge transport (danube) discharging,on truck,custom clearance (rinz) Inland transport (rinz-zilina) KMS Deliver to factory custom clearance (zilina) Installation & commisioning 25 3 Normal : 61d short : 55d 35 13 4 Transport duration (departure~custom clearance) 33 RotemBMI(SSU)
6
BETTER SOLUTIONS 3-1. Shipment scope Requirement at the time of loading partyworking scope ROTEM documents : Invoice, Packing list, export license, insurance inland trucking & storaging warehousing & inport shuttle in time sailing (rotem & wia) final cargo readiness : end of aug. BMI(SSU) charter vessel berth arrangement loading issue B/L transport shcedule management
7
BETTER SOLUTIONS 3-2. Loading operation loading operation
8
BETTER SOLUTIONS 3-3. Route and duration of ocean transportation Suez Constanza Rotterdam Masan Typical Liner (35days) Charter vessel (25days)
9
BETTER SOLUTIONS 3-4.1 Vessel spec. & transit time (Typical Liner) Vessel Type : Typical Liner (Multi-purpose heavy lift) Gross tonnage : 24,000Ton Net tonnage : 11,000Ton Length(Over All) : 200M Breath(Mid) : 28M Depth(Mid) : 15M Mouldet Draft/Dwt : 11M/30Ton Built : Year 2004 Classification : G. Lloyd + 100 A5 E Cargo Hold : No.1~5 Hold with Tween Deck Speed : 18~20 Knots
10
BETTER SOLUTIONS 3-4.2 Vessel spec. & transit time (Charter Vessel) Vessel Type : Multi-purpose heavy lift Gross tonnage : 9,000Ton Net tonnage : 5,000Ton Length(Over All) : 120M Breath(Mid) : 20M Depth(Mid) : 12M Mouldet Draft/Dwt : 9M/20Ton Built : Year 2000 Classification : G. Lloyd + 100 A5 E3 Cargo Hold : No.1~2 Hold with Tween Deck Speed : 15 Knots