1 Request for Change of Scope : $3.5M UI Claims Modernization Presented to PCC, April 28, 2010
2
2 Scope Change Overview Current Original certification accounted for six (6) subprojects containing nineteen (19) initiatives {See Slide 4 for budget listing} Initial efforts targeted legacy systems Project tracking and budgetary restrictions limited system improvement opportunities
3
3 Scope Change Overview Proposed Current request accounts for five (5) subprojects containing seven (7) initiatives {See Slide 5 for budget listing} Efforts target forward-facing technology Sub-projects can be leveraged for future growth opportunities Budget, as proposed, already NMORR approved.
4
4 Original Budget
5
5 Proposed Budget Note: This budget is the version approved by NMORR.
6
6 Project Status
7
7 Summary New scope will support future agency direction New IVR network infrastructure can be leveraged to provide future UI Claims enhancements
8
8 Thanks! Questions?