Port of Duqm Company profile
Muscat, January 2012
2
Contents Introduction. Company creation. Regional facts.
Development plan ( Commercial Berths and Dry Dock). Port key figures Port stakeholders.
3
A. Introduction Early 2000 : GOSO embarked on a visionary project to create a new port in Duqm. 2007: MoTC started to build the first phase of the port. 2010: Port of Duqm Company (PDC) was created. April 2011: concession agreement initialled between GOSO and PDC. May 2011: port starts receiving vessels for the Shipyard (ODC). Mid 2012: first cargo handling operations (cement, project cargo, bulk).
4
B. Company Creation Port of Duqm Company SAOC (PDC) is a Joint Venture between Consortium Antwerp Port and the Government of the Sultanate of Oman. 20 April 2011: Concession agreement for PDC was initialled. Duration of the concession: 28 years (3 years + 25 years). The Concession is for the operation, management and marketing of the port.
5
37 Mn TEU – 11% average growth
C. Regional facts Port Traffic 24.1 Mn -12% 11.2 Mn -10% Total Tanshipment Market 37 Mn TEU – 11% average growth 1.9 Mn -7% The pyramid shows each region’s total and gateway traffic in Million teu and growth rate over last 10 years ( ) Mid-East Mid-East Red Sea ISC East Africa East Africa ISC
6
D. Development Plan Duqm Area
7
D. Development plan PORT
8
D. Development plan
9
D. Commercial Berths
10
D. Dry Dock
11
E. Port key figures Area: Breakwaters:
Total port area: 197 km2 , of which 60 km2 is land Rentable port-related Industrial zone area: about 6,000 hectares Breakwaters: Lee breakwater: 4.1 km Main breakwater: 4.5 km Water depths: to allow safe reception of vessels with capacity up to DWT Approach channel: -19m Quays: -18m (commercial berths) Indicative Capacity of Phase 1 (2.3km berth, 80 ha. terminal, 900 ha. back-up storage): Multipurpose terminal : 0.8 Mt Container terminal : 3.5 M TEU Dry bulk terminal : 5.0 Mt Phase 2: at least 10km quay length and/or several liquid jetties (still to be tendered)
12
E.Port Stakeholders Oman Dry Dock
Commercial Quay (container, bulk & multi-purpose terminals) Railway station Port of Duqm Company (pilotage, maritime safety, emergency response, …) ROP (customs, immigration, civil defence) Ministry of Health MECA Liquid Terminal Containers back-up storage area Government berth (ROP, Royal Yacht, …) Light industry area Logistics area Future expansion area Liquid Storage
13
Thank you very much Shukran Port of Duqm Company