Review of Section L – Maintenance and Operational Planning A Presentation to the Transmission Workstream – November 2005 Steve Gordon, ScottishPower Energy Management Limited
2
Overview Relevant changes since 1996 What Hasn’t Changed much? Time for a review? Current Mod NG response and proposed mod Other Issues for Consideration
3
Changes To the Market Advent of competition Growth of the CCGT market Increase in the number of directly connected sites to NTS Advent of NETA then BETTA DN Sales & diversity of ownership of transportation network Closer alignment of the gas and electricity regimes Move towards import dependency and a requirement for demand-side response.
4
What Hasn’t Changed Much during that time? NExAs – specifying information about offtake rates, notice periods and planned maintenance Section L!
5
Time for a Review? Yes
6
Mod 060 Discussed with NGT and sent to consultation on 20 th October Main Aims: –Ensure that information is provided to maintenance affected points in the spirit of the intent of the code. –Ensure confidentiality of that information.
7
NGT Initiative Earlier publication of information on system affected points Early confirmation of window Earlier confirmation of exact dates New mod (discussed today) codifies this approach
8
Other Issues Distribution and Transmission Maintenance Programmes Classification/Categorisation of Different Types of Works Publication of Inspection Programme Information Incentivising an Efficient Maintenance Programme