1 Metro Vancouver’s Seymour Capilano Filtration Project
Howard Dallimore Senior Project Engineer Metro Vancouver

2 The largest filtration plant in Canada and one of the biggest of its kind in North America.
Treats water from two watersheds and includes a 16,000 HP pumping station, twin tunnels each 7.1 km long and a 2 MW energy recovery facility. Spent filter backwash water is treated and over 98% is recycled to the head of the plant. The world’s largest ultraviolet disinfection system.

3 Includes a series of features to maximize energy efficiency.
Extensive use of sustainable and environmental technologies used in its design and construction. The plant is fully automated and integrated with Metro Vancouver’s SCADA system.

4 Water Sources Wholesaler to over 2 million people
3 protected lake supplies: Capilano Seymour Coquitlam

5 Water Quality Concerns
Corrosion Waterborne Disease Turbidity Re-growth

6

7 Turbidity Events

8 Seymour-Capilano Filtration Project

9 Elements of the Seymour-Capilano Filtration Project (SCFP)
Capilano Pumping Station Capilano Energy Recovery & Break Head Tank Twin Tunnels linking Seymour and Capilano sites Seymour-Capilano Water Filtration Plant

10

11 Filtration Project Rendering

12 Artist’s Rendering of Seymour-Capilano Filtration Plant

13

14 Seymour- Capilano Filtration Plant

15 Seymour- Capilano Filtration Plant

16 Filtration Plant

17 Guard House

18 Pre-Treatment Building

19 Pre-Treatment

20 Flocculators and Filters

21 UV Units - Filter Gallery

22 UV Disinfection Unit

23 OMC Building

24 OMC Lab

25 OMC Control Room

26 Filtration Plant Post Treatment

27 Geothermal System

28 Inside Clearwells

29

30 Back Wash Water Treatment Tanks

31 Residuals (Sludge) Collector

32 Residuals Building

33 Residuals

34 Residuals

35 Sustainable Technologies
Economic Prosperity Community Input Aggregate mined from Lower Seymour Conservation Reserve Concrete batch plant located north of plant Eco Smart concrete Stormwater management Protected stand of mature trees Amphibian pond conservation Green Building Design – LEED Geothermal Heating and Cooling Energy and water conservation strategy Green roof technologies Environmental Integrity Social Well - Being

36 Siting, Development and Protection
Protected Tree Stands Frog Pond LSCR Parking Lot

37 Plant Salvage 2003 Municipal Salvage Non-profit Organizations
Evergreen School Salvage Event Public Salvage Day

38 Landscaping and Habitat Creation

39 Site Restoration

40 Landscaping on Clearwell
Sept. 29, 2009