MS Project Tutorial EMEN. Entering Project Properties Choose File Properties Click the Summary tab You can now enter general information about the project.

Similar presentations


Presentation on theme: "MS Project Tutorial EMEN. Entering Project Properties Choose File Properties Click the Summary tab You can now enter general information about the project."— Presentation transcript:

1 MS Project Tutorial EMEN

2 Entering Project Properties Choose File Properties Click the Summary tab You can now enter general information about the project You can get a preview image of the file in the Open File dialog box when you open the file if you check the Save preview picture box

3 Setting Project Timing Choose Project Project Information Click on the arrow to the right of Start date and a calendar appears Enter the project start date Use the Calendar drop down option to select the type of work days: Standard: 8 a.m. to 5 p.m., one hour lunch 24 hour: work continues throughout entire day Night Shift: Midnight to 8 a.m., one hour break at 3 a.m.

4 Set Up Non-Working Days Choose Tools Change Working Time Use default or set specific days by clicking on them Click the Nonworking Time radio button

5 Create a New Task Click the Gantt Chart icon on the View bar on the left side of the project screen. Click on the task line where you want to enter a task. The Task Information box appears. Enter the task name and duration. The task name and duration will appear on the Gantt Chart.

6 Set Task Properties Click the Advanced tab on the Task Information box. Select task type and choose either Fixed Units (assigned resource percentage stay the same), Fixed Duration (Task time independent of resources), or Fixed Work (required work determines the task length). For a Milestone, enter 0 in the Duration box Set the task constraint type depending on when you wish the task to start relative to others and any slack available.

7 Linking Tasks To link a task click on Predecessors. Enter the linked preceding task by ID or name and select the type of linkage and lag. The current task will be moved on the Gantt chart to adhere to the required logic. Note, it is a good idea not to enter dates when setting up tasks after the first one if they are linked as the logic constraints determine start and finish dates. Only enter durations.

8 Summary Choose View Reports to select various summaries of what has been entered.

9 Summary Gantt Chart view of entered tasks

10 Summary PERT Chart view of entered tasks

11 Demoting Tasks Click the indent arrow keys on the tool bar to demote a task such as the two shown below. This causes the preceding task to become a Summary Task. Tasks can also be promoted

12 Assigning Resources On the Gantt chart click on a task name, and the task information box appears. Click on Resources tab. You can then enter individual resources and the amount of time each will spend. For material resources, the assignment unit is the number of units. You can assign someone more than 100% if you know overtime is allowed.

13 Assigning Resources You can also assign resources by clicking the Assign Resources symbol on the standard tool bar. Then, you can enter all the resources for that task

14 Assigning Resources Click on More Views Task Details Form to get a complete task resource summary. More Views is the last icon in the left column.

15 Assigning Resources Click the Resource Sheet view icon on the left side of the side of the screen. A summary of assigned resources appears for that task.

16 Assigning Resources To level resources, choose Tools Resource Leveling If you choose the Automatic radio button, Project will apply leveling anytime a conflict occurs.

17 Assigning Costs On the Resource Sheet, double click on a resource name cell, and the Resource Information box appears. Click on the costs tab, and you can enter rates. You must enter both the $ amount and time frame such as hours (h). You can also enter a per use cost for an entire job as for a contractor. Note the cost accrual box. You can enter the cost to be accrued at the Start, End, or prorated during the task.

18 Assigning Costs Once all costs and times are entered, click on Tools Tracking Tracking Save Baseline. When you choose the Resource Sheet view, you will see the total baseline cost rolled up for each resource for each task.. Notice as you track usage during the project, the actual cost and variance will be calculated.

19 Assigning Costs To see a summary of resource cost information, click on the Resource Sheet icon. From the toolbar, choose View Table Entry You will now see a complete view of resource cost information with accrual method.

20 References A good, practical source for “how to” use MS Project, you can try: Microsoft Project 2000 for DUMMIES, Quick Reference Nancy Stevenson, Hungry Minds, Inc., N.Y. ISBN: 0-7645-0717-6


Download ppt "MS Project Tutorial EMEN. Entering Project Properties Choose File Properties Click the Summary tab You can now enter general information about the project."