1
High level overview of HUB upgrade and market release strategy June 2010
2
Two Versions of the MPCC –MPCC 15.1 (existing test W2000 machine, but with Schema 8 installed on it) –MPCC 16.0 (new W2003/XP machine with schema 8)
3
IPT Process
4
IPT Strategy To replicate the to-be situation, at least one MP is required to run IPT using MPCC 15.1 and, at the same time, at least one will use MPCC 16.0 This is a change to the process that was briefed at the November IGG
5
Schema Release March 19 th. Dispatch upgraded schema 8 and two CDs to each MP. –CD1 MPCC 15.1 –CD2 MPCC 16.0
9
Cutover
10
By Thursday June 24 th - Formal go/no-go confirmation from CER Friday June 25 th –13.00 - Confirmation from RMDS –18.00* - Market Participants are asked not to send in any Market Messages after this point Saturday June 26 th –Morning* - Application of changes –Afternoon* - Connectivity testing All communications will be via RMDS over the cutover weekend * Times subject to validation through dress rehearsals
11
Contingency/Rollback
12
Go/No-Go Decision prior to weekend Hub Upgrade will precede the Market Release Planned to involve TSO and MP1 in testing the hub upgrade Therefore will require rollback plans for both their backend systems On success, apply SAP transports to Central Market System – point of no return Hub Upgrade
13
Consists of SAP IS-U transports, RMP Extranet changes and MPCC 15.1 upgrade Any issues with the Market Release will be addressed through fixing forward i.e. application of corrective transport Market Release
14
Fallback is to switch production IP back to MPCC 15.1 in the event of a problem with MPCC 16.0 MPCC 16.0 upgrade
15
Questions?