2
http://www.kare11.com/news/article/1044895/391/Mine- expansion-to-claim-vital-Iron-Range-highway KARE 11 News Story 2
3
Today’s Topics 3 Project Updates Layout Ongoing activities Schedule Dates Economic Study
4
Draft EIS Layouts/preliminary plans Cost Estimates Hydrogeology Study of Rouchleau pit Project Delivery/Schedule Methods Upcoming/Ongoing Activities
5
Dewater about 25 feet build in dry Possible locations Virginia Lakes Enterprise Pit Magneka Creek 3 months to dewater @ 20,000 gpm Will not affect City water supply. Rouchleau Pit Study for E1a
6
Anticipated Schedule (11/07/13) Milestone TasksTarget Dates Draft EIS and Public HearingApril 2014 Identification of Preferred AlternativeJune 2014 Final EISFebruary 2015 FHWA Record of DecisionMay 2015 Start constructionJune 2015 Open to trafficOctober 31, 2016
7
Coffee & Conversation Thursday, December 5 10-11 am MnDOT Coffee & Conversation January 2, 2014 10-11 am MnDOT Upcoming Meetings