Forest Lake EDA Meeting June 27, 2011
2
CR 2 and I-35 Bridge/Interchange First Ave NW (Backage Road) CR 2/Broadway Avenue Roadway Utilities Hardwood Creek Pedestrian Bridge Impact of Possible State Shutdown (July 1) Communication Update
3
Bridge Removal Week of May 9 Bridge Removal between 9PM-6AM 4 nights
4
Interchange Construction Construction on temporary ramp Surcharge construction
5
Bridge Construction Pouring concrete on east abutment stem wall A look at the east abutment Prior to backfilling
6
Bridge Construction Excavation for the center pier (In I-35 median)
7
Open to Traffic– Friday, July 1
8
To begin after the Backage Road (First Ave NW) is open to traffic.
9
Watermain work Directional boring utility work
10
May 6, 2011
11
Pouring the bridge deck Painting the walls
12
The Pedestrian Bridge will be open from July 1-July 4. The Bridge will close again beginning July 5. The Pedestrian Bridge will be open at the end of July. Chain-link fencing is temporary.
13
Washington County Engineer Wayne Sandberg to give a more detailed presentation at City Council meeting tonight – 7PM.
14
Broadway Bulletin- 31 Businesses participating - 15 distribution sites Go Local Discount Card- 18 Businesses participating - Expires 12/31/11 Where’s the Concrete Truck? Arts in the Park
15
Facebook: - 35 people follow the page - posts have gotten up to 250 Impressions Twitter:- 113 Followers YouTube:- Construction Videos - “A View of Broadway” Videos Website:- 1384 unique visitors (June) - 2228 total visits (June)
16
Any Questions?