Municipal State Aid (MSA) Forest Lake, MN May 7, 2013
2
Overview: MN Statute 162.09 Covers Rules and Regulations of the State Aid System Cities with a Population of 5,000 or More are Eligible to Become a State Aid City Trunk Highways, CSAH, and MSA Systems are Funded by the MN Gas Tax, Tab Fees, and Vehicle Sales Tax Current Gas Tax = 25 ₵ /Gallon, Plus 3.5 ₵ /Gallon Debt Service Surcharge
3
MSA System Statistics: 147 State Aid Cities (17% of 853 Cities) – 83 Metro – 64 Greater Minnesota Current MSA System Totals 3,400 Total Miles
4
MSA System Statistics (cont.):
5
MSA Financial Data: Total 2013 MSA Allocation = $150 Million – Largest Allocation is Minneapolis = $13,600,000 – Smallest Allocation is Falcon Heights = $160,000 – Forest Lake Allocation = $1,107,316 Commission of Transportation will Determine Each City’s Apportionment by February 1 st of Each Year
6
MSA Financial Data (cont’d): Reimbursement to Cities Broken into Construction and Maintenance – Construction reimbursements can only occur after the City spends money on a project and requests reimbursement. o Forest Lake construction allocation = $830,487 – Maintenance allocations are directly sent to the City o Forest Lake maintenance allocation = $276,829 o Can be increased if requested by the City (35% Max) o Current requests are set at 25% of total allocation
7
MSA Road Requirements: Road must be entirely within City limits Beginning and end of segment must be one of the following: – Another MSA Street – County State Aid Highway – State Highway Total MSA mileage must be 20% or less of total mileage within the City To use MSA funds, road must meet design requirements or obtain a variance.
8
MSA Management Process:
9
MSA Management Process (cont.): Systems Revision Request – Request to DSAE – Optional item used to add, delete or re-designate mileage – No standard form / format (Letter is Acceptable) – Requires a Council Resolution Needs Update – Process currently being modified Traffic Counts – Due every 4 years (2014) – Expense to complete cannot use MSA Funds
10
Metro Municipal Traffic Counting Schedule
11
Needs Determination System Change Guiding Principles Simple – New system should be easy to learn and use Credible –Transparent, accountable and no gamesmanship Flexible – Software changes easily implemented(MSB) – Flexibility in use of dollars Equitable – Needs computations are more realistic (ADT)
12
Needs Determination System Change (cont.) Continual needs approach – all segments will draw needs. Eight typical sections based on existing ADT – No projection factor – Used for needs estimation, not design – actual construction widths could differ SectionADTTypical Section Width (ft) 1026 21 - 49928 3500 - 1,99934 42,000 – 4,99940 55,000 - 8,99948 69,000 – 13,99954 714,000 – 24,99962 825,00070
13
Needs Determination System Change (cont.) Uniform quantities for each section – Urban design quantities for all segments – Uniform soil factor – Quantities based on MnDOT approved design SectionWidth (FT)20 Year ESALR-ValueClass 5 (IN)Bituminous (IN) 126N/A 64 22883,0001564 334177,00015104 440443,00015164 548718,00015194 6541,117,00015195 7621,995,00015206 8703,104,00015216
14
Forest Lake - Mileage County and Highway Miles Trunk Highways17.42 Miles Trunk Highway Turnbacks0 Miles County State Aid Highways4.10 Miles County State Aid Highway Turnbacks8.51 Miles Total County and Highway30.03 Miles
15
Forest Lake - Mileage Basic Miles Municipal State Aid Streets23.74 Miles County Road Turnbacks (MSAS)0 Miles County Roads (excludes MSAS)5.64 Miles Other Local Roads and Streets101.94 Miles Total Basic126.87 Miles Maximum Allowable State Aid Mileage = 0.20 x 126.87 Miles = 25.37 Miles
16
2013 State Aid Streets
17
2013 State Aid Streets Revisions
18
Removal ADT