Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd
2
Date: 11/03/20092 Overview of Presentation Vault 9 Design Current Status
3
Date: 11/03/20093 Vault 9 Vault 9 Design
4
Date: 11/03/20094 Plan Overview Scheme ANDY – Can you insert the base site plan that you are using to show the new material facility plan – Showing the Current infrastructure
5
Date: 11/03/20095 Proposed Development
6
Vault 9 Liner Details
7
Date: 11/03/20097 Vault 9 Current Status
8
Date: 11/03/20098 Bulk Excavation – 100% Complete
9
Date: 11/03/20099 Rail Deliveries – Aggregate, Reinforcement & Ancillaries
10
Date: 11/03/200910 Rail Deliveries – Port of Workington
11
Date: 11/03/200911 Rail Deliveries – Millom Main Line Loading
12
Date: 11/03/200912 West Outer Wall Construction - 95% Complete
13
Date: 11/03/200913 Secant Pile Wall – 100% Complete
14
Date: 11/03/200914 BES Bottom Layer - 80% Complete
15
Date: 11/03/200915 Geomembrane, Geotextile & Drainage Layer – 45% Complete
16
Date: 11/03/200916 Vault 9 Floor Slab - 22% Complete
17
Date: 11/03/200917 West Inner Wall - 60% Complete
18
Date: 11/03/200918 Partial Handover – 21 st July 2009
19
Date: 11/03/200919 Delivery Schedule Partial Turnover to Operations – July 2009 Operational Safety Case Approved First HHISO –July 2009 Contract Completion – January 2010
20
Date: 11/03/200920 Vault 9 Questions