Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd.

Similar presentations


Presentation on theme: "Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd."— Presentation transcript:

1 Vault 9 Project Update 9 th September 2009 Paul Pointon – Site Project Delivery Manager LLW Repository Ltd

2 Date: 11/03/20092 Overview of Presentation Vault 9 Design Current Status

3 Date: 11/03/20093 Vault 9 Vault 9 Design

4 Date: 11/03/20094 Plan Overview Scheme ANDY – Can you insert the base site plan that you are using to show the new material facility plan – Showing the Current infrastructure

5 Date: 11/03/20095 Proposed Development

6 Vault 9 Liner Details

7 Date: 11/03/20097 Vault 9 Current Status

8 Date: 11/03/20098 Bulk Excavation – 100% Complete

9 Date: 11/03/20099 Rail Deliveries – Aggregate, Reinforcement & Ancillaries

10 Date: 11/03/200910 Rail Deliveries – Port of Workington

11 Date: 11/03/200911 Rail Deliveries – Millom Main Line Loading

12 Date: 11/03/200912 West Outer Wall Construction - 95% Complete

13 Date: 11/03/200913 Secant Pile Wall – 100% Complete

14 Date: 11/03/200914 BES Bottom Layer - 80% Complete

15 Date: 11/03/200915 Geomembrane, Geotextile & Drainage Layer – 45% Complete

16 Date: 11/03/200916 Vault 9 Floor Slab - 22% Complete

17 Date: 11/03/200917 West Inner Wall - 60% Complete

18 Date: 11/03/200918 Partial Handover – 21 st July 2009

19 Date: 11/03/200919 Delivery Schedule Partial Turnover to Operations – July 2009 Operational Safety Case Approved First HHISO –July 2009 Contract Completion – January 2010

20 Date: 11/03/200920 Vault 9 Questions