FDOT District 6 ITS Project Update Manuel Fontan, E.I. ITS Project Manager.

Similar presentations


Presentation on theme: "FDOT District 6 ITS Project Update Manuel Fontan, E.I. ITS Project Manager."— Presentation transcript:

1 FDOT District 6 ITS Project Update Manuel Fontan, E.I. ITS Project Manager

2 Outline  ITS Program Updates  Other Deployment Updates  ITS Operations Contract Updates  Operational Updates

3 ITS Program Updates  US 1/SR 5 Estimated Completion Date: April 25, 2008 4 DMS 17 CCTV 6 Detectors

4 ITS Program Updates  I-395/SR A1A & Port of Miami Letting Date: October 9, 2007 1 DMS (Port of Miami) 8 CCTV (Mainline); 2 CCTV (Port of Miami) 10 Detectors (Mainline)

5 ITS Program Updates  SR 826 Letting Date: October 9, 2007 3 DMS 6 New CCTV (4 on Interchanges and 2 for DMS Verification); 4 Existing 37 Detectors

6 ITS Program Updates  ITS Technical Consultant Services Letting Date: Approximately May 2008 Executed: Approximately July 2008 Budget Amount: $ 1.5 Million/5 Years

7 ITS Program Updates  95 Express (Miami-Dade County) – Phase 1A (SR 112 to GGI) Design Build Initiated Equipment/Devices:  Tow  CCTV  Toll Rate Signs  Lane Status Signs (1 Line DMS) Estimated Completion Date: Summer 2008 Estimated Completion Date - All phases: Summer 2010  Ramp Metering Initial metering will be for the 8 NB ramps on the 95 Express Lanes limits Turned on simultaneously with 95 Express Lanes

8 Other Deployment Updates  June 2008 FDOT District 6 SunGuide™ TMC Intranet Release 2.0 RRDIS Release 2.0

9 ITS Operations Contract Update  Notice to Proceed: December 17, 2007  Staff Transitioned: January 14, 2008  24 positions  TMC Operations: 16 Positions 1 TMC Manager 1 Assistant TMC Manager 1 Road Ranger Contract Manager 2 Shift Supervisor 2 TMC Lead Operators 9 TMC Operators Contract Support: 3 Positions 1 Contract Project Manager 1 Office Manager 1 Receptionist (Front Desk)  IT: 5 Positions 1 IT/ITS Maintenance Manager 1 Network Administrator 2 IT Administrators 1 Software Systems

10 Operational Updates  February 2008

11 Operational Updates  February 2008

12 Operational Updates  February 2008

13 Questions? Manuel Fontan, E.I. FDOT District 6 (305) 499 - 2493 Manuel.Fontan@dot.state.fl.us


Download ppt "FDOT District 6 ITS Project Update Manuel Fontan, E.I. ITS Project Manager."