Download presentation
1
Safety in Excavation
2
EXCAVATION Reference Standard IS : 1992
3
Excavation Excavation.
Any man made cut, cavity or depression in the earth’s surface formed by earth.
4
Excavation Hazards Soil Collapse Utilities Hazardous atmospheres
Adjacent structures Falls / Falling loads Access / Egress Vehicle traffic Mobile equipment Water accumulation Cave-in
5
…..Excavation hazards Cave-in / Soil collapse Improper shoring.
6
Excavation hazards Collapse of shoring Falling loads
7
…..Excavation hazards Slip & fall of workmen Utilities
8
…..Excavation hazards Vehicular traffic Adjacent structures
9
…..Excavation hazards Mobile equipment. Access / Egress
10
Soil collapse
11
So, What is required ?
12
Prior to Excavation Obtain a work permit Check Ground / Soil condition
Check Ground / Surface Water Check the Location of Water Table Check Under ground / Overhead utilities Adjacent buildings Dynamic load / Traffic
13
Soil Classification Type A : Clay, sandy clay, clay loam Type B :
Angular gravel (similar to crushed rock), silt, silt loam, sandy loam Type C: Gravel, sand, loamy sand,Submerged soil or soil from which water is freely seeping; or Submerged rock that is not stable
14
Preventing Soil Collapse
Soil classification (Type a, b, or C) Sloping Benching Placing a shield. Shoring(Timber / Aluminum shoring Sheet piling
15
Your choice of protection
Sloping Benching Shoring Shields Designed by a Registered Project Engineer
16
Simple Sloping Stable Rock : 900 Type A - 3/4:1 530
Short term up to 12’ -630 Note :Greater than 20 feet deep shall be designed by a registered professional engineer.
17
Simple Sloping -Type A Soil
Unsupported Vertically-Sided Lower Portion <12 ft Unsupported Vertically-Sided Lower Portion <8 ft
18
Simple Sloping -Type A Soil
Supported or Shielded Vertically-Sided Lower Portion
19
Simple Sloping Type B - 1:1 450 Type C - 1½ :1 340
Note :Greater than 20 feet deep shall be designed by a registered professional engineer.
20
Benching Type A Type B (cohesive)
21
Basic components of shoring
22
Shoring in Footing foundation
OUTWARD SLOPE ( 35* TO 40*) CONSIDERING ONGOING RAINY SEASON
23
Arrangements in Water Logged Area
SUPPORT TO THE WALL OF EXCAVATED PIT
24
Timber Shoring Installations
REFER TO DESIGN ENGR.
25
Utilities Underground PERMIT SYSTEM
26
EFFECTS OF UTILITIES ABOVE GROUND UNDER GROUND
27
EFFECTS OF UTILITIES EXPLOSION FIRE
28
UTILITIES Obtain work permit and get clearances from the concerned
PREVENTION Obtain work permit and get clearances from the concerned Electricity Water & Sewage Pipeline Communication Oil & Gas Pipe Line Use Detectors ( for More Reliable)
29
Water Accumulation Ground water Surface water
30
Hazardous Atmospheres
Never Start Work if, Oxygen Level less than 19.5 % Permissible limit of the toxic gases exceeded. More than 20 % of Lower Explosive Limit. PRECAUTIONS Ventilation to over come the above said. Blocking the source, incase of toxic and flammable gases. (Using other effective controls to reduce the level of atmospheric contaminants to acceptable levels)
31
Adjacent Structures Ensure structure stability Shoring Bracing
Evaluation by Professional
32
FALLING LOAD Gravity Weight of soil pile Weight of near by structures
Weight of personnel &equipment Vibration PREVENTION Never operate a construction equipment within 2.5 m from the edge of the excavation. Stacking the material 1 Meter away from the edge of the excavation.
33
Access Ladders – Ramps with slope not more than 15o
@ every 9.14 m Length – Normal Operations @ every 4.6 m length – Hazardous operation Ramps with slope not more than 15o Stairs cut on earth
34
Vehicle Traffic Control Measures Traffic Management Plan
Traffic Safety Vests Fencing Illumination
35
Traffic Control Device & Vest
36
Fencing Physical barricades required always
Hard Barrication shall be provided, in the fall prone areas and if depth is more Physical barricades required always Must be placed 2m away from excavation edge. Standard fall protection required for vertical falls over 1.3m Traffic diversions Pedestrian walkway diversions
37
Caution Signs Reflective Cone Barricades
38
ILLUMINATION Temporary Lightings: Sufficient Area Lighting.
Emergency Lighting with Power back up.
39
Excavation Inspections
Daily Inspections by Competent Person Start of shift, as needed, following rainstorms or other hazard-increasing event Possible cave-ins Protective system failure Water accumulation Hazardous atmospheres
40
Beyond All
41
Safety awareness – Supervision
Develope - personnel interested on Safety, Safe work procedures considering the ground realities. Awareness and motivating the supervisors concerned, Develop system to report, analyze and prevent Near-miss cases. Developing gang leaders and attitude,
42
Any Questions ?
43
Thank You & Have a Safe day
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.