Edward Downer Elementary School Playfield Renovation Status Update 10/14/14.

Similar presentations


Presentation on theme: "Edward Downer Elementary School Playfield Renovation Status Update 10/14/14."— Presentation transcript:

1 Edward Downer Elementary School Playfield Renovation Status Update 10/14/14

2 Construction Manager:Gabriel Fortich (SGI) Inspector of Record:Man Wah Cheng Architect of Record:BCA Architects General Contractor: Maggiora & Ghilotti, Inc.

3  Fine grading to commence 10/20/14 -11/24/14  Sod Installation to commence on 10/27/14 – 10/31/14  Irrigation booster pump 11/6/14 – 11/13/14  Field complete 11/15/14

4

5  Project Duration:180 (Calendar Days)  Notice To Proceed Date: May 19, 2014  Completion Date:Nov 15, 2014  Percent Complete: 90%  Base Contract Amount:$563,226.00  Change Order to date:.1%

6 Graded Site

7 Landscape Planting