20/01/09 OPERA general meeting Nagoya CNGS report
2
Expectations for 2008 (from collaboration meeting in June 08): nominal intensity for 2008 of 2x10E13 pot/extraction 123 effective beam days from the SPS schedule; super-cycle of 48 s (including LHC cycle), 80% efficiency, during day- time (50% of the time); super-cycle 42 s (removed MD cycle) during the nights, we would eventually expect ~2.28x1019 pot, ~120 interactions/week, ~2200 interactions integrated over the whole 2008 run. 2008 budget: Intensity 2.0 E 13/extraction reached in August First part of the run very inefficient due to many general problems occurred at the CERN machine complex Recovered performance in October due to the LHC accident and semi-dedicated operation mode
3
Extraction 1 Extraction 2 2.0 E 13 pot Beam loss, vacuum accident 27/6-2/7 2.0 E 13 pot Fri 20/6 3 cycles Unix Time pot Wed 18/6 17:00 Start of commissioning at low intensity Long MD stop + MTE kicker problem 7/7 6:00 – 10/7 12:00 10/7 21:00 Earth fault on the PS magnet PS magnet repair no beam until Fri 18/7 23:08 18KV cable accident 25/7 PS septum + Long MD 8-14/8 3/11 8:00 Horn filters PS vacuum CNGS quadrupole MD Horn filters
4
60% average efficiency
5
Extraction 1 (pot) Extraction 2 (pot) Average intensity: 1.75 E 13 pot Average intensity: 1.84 E 13 pot CNGS distribution of the intensity per extraction during all the run
6
Super-cycle without MD
7
Semi-dedicated mode
8
1.782 E 19 pot Beam loss, vacuum accident 27/6-2/7 Unix Time pot Wed 18/6 17:00 Start of commissioning at low intensity 10/7-18/7 Earth fault on the PS magnet Long MD stop + MTE kicker problem 7/7 6:00 – 10/7 12:00 3/11 8:00 1.782 E 19 pot 18KV cable accident 25/7 PS septum + Long MD 8-14/8 Horn + PS vacuum Week 1/9 CNGS quadrupole 14-17/9 6-8/10 MD Horns filters 19-20/10 Half of statistics in October
9
Past CERN performance for the running of the West Area Neutrino facility (Chorus+Nomad) 2008
10
Statistics: Increase in the duty cycle since September 24th (suppression of LHC pilot cycle) further increas after November 6th (stop of north area) allowed to partially recover the bad performance since the beginning of the run, about 1E19 pot collected during this last period. Final numbers: 1.782 E 19 pot collected, corresponding to 10058 on time events and 1690 candidates in the bricks. Number of events expected with 1.762 E 19 pot (black outs removed) = 1700
11
Multi-turn extraction: A necessary tool in order to achieve nominal beam performance -Remove bottleneck due to beam losses at the extraction from the PS - Cleaner beam for SPS, less crytical tuning of the machine - Less radiation damage, less troubles, better efficiency Under commissioning since the beginning of the run First extraction to SPS achieved on August 1 st
12
MTE Work not finished, to be continued next year (suffered a lot from low resources) Tests perfomed even with CNGS beam at the end of the run, last day neutrinos sent to LNGS with 1.3 E 13 pots/extraction in one over five CNGS cycles CT extraction not dismantled, will work in parallel still at the beginning of next year Once MTE works it will be needed a robust effort to improve the PS performance, we have to make sure that there will be resources for that
13
Start May 14th
14
End November 23rd
15
What we learnt for 2009 ? Average efficiency of 80% was achieved in the last part of the run Intensity of 2.0 E 19 achieved 2.4 E 19 to be demonstrated MTE work has to be finished ~couple of months then PS tuning has to be performed in order to increase the intensity Expectations for 2009: 173 days 48s supercycle 80% efficiency 2.4 E 13 pot/extraction 3.6 E 19 pot 3500 events