BOTTLENECK STUDY UPDATE Pedro Orso-Delgado District Director District 11
2
Presentation Outline Review Completed Bottleneck Study and Findings Provide Update of Improvements Completed and Underway at: Otay Mesa/Mesa de Otay Port of Entry San Ysidro/Puerta Mexico Port of Entry Future Activities
3
Background F 12/02 Caltrans Tasked by JWC to Address Transportation Infrastructure Supporting POE’s F Develop Border-wide & Multimodal Bottleneck Methodology for U.S.-Mexico F 11/04 JWC approved the Final Report of Bottleneck Study - Phase I Case Study: San Diego-Tijuana Gateway
4
Study Objectives & Accomplishments The San Diego-Tijuana gateway was used as a test-bed Documented results of methodology including challenges and recommendations FThe study can be used as a common U.S.-Mexico border-wide framework Successfully developed a methodology to identify low-cost/high result recommendations
5
N3 N4 N1N2 N5 N6 Methodology
6
MEXICO U.S.A. Otay Mesa Case Example MEXICO EXPORT U.S. IMPORT
7
Otay Mesa/Mesa de Otay Operational, Minor Infrastructure and Safety Improvements at Northbound & Southbound Truck Routes Improve turning radii at various locations Pave emergency lane Re-route empty lane Add traffic signal Increase capacity via additional lanes Install concrete barriers Identify Bottlenecks and Proposed Improvements
8
U.S.A. MEXICO 6 5 2 3 4 1 11 12 7 10 9 18 17 16 15 8 13 14 Southbound Northbound Otay Mesa/Mesa de Otay
9
Northbound Key Improvements Ultimate Expansion 8 lanes $600,000 to expand from 3 to 4 lanes 4 Lanes completed
10
Otay Mesa/Mesa de Otay Southbound Key Improvements Increase Turning Radius and Re-route Empty Trucks
11
$16.9 Million - Major Expand from 2 to 9 Lanes Plus other Southbound Roadway Improvements 9 Lanes DRUCKER LANE Otay Mesa Southbound Truck Route Major Improvements SIEMPRE VIVA RD. SOUTHBOUND PORT OF OTAY MESA CARGO 5 Lanes 4 Lanes Status: City working on Environmental Document
12
OTAY MESA POE NORTHBOUND INFRASTRUCTURE IMPROVEMENTS
13
Otay Mesa/Mesa de Otay Southbound Key Improvements
14
Otay Mesa Northbound Truck Improvements $1.0 million Expand from 3 to 8 Lanes Mexico Export U.S. Import 8 Lanes
15
Otay Mesa Northbound Truck Improvements $1.0 million Expand from 3 to 8 Lanes 8 Lanes Mexico Export U.S. Import
16
San Ysidro/Puerta Mexico Operational, Minor Infrastructure and Safety Improvements for cars and pedestrians Increase number of SENTRI lanes Expand access to SENTRI lanes Extend Pedestrian Bridge Better utilization of all through lanes Create secondary turn pocket Enforce “No Parking” zones Identify Bottlenecks and Proposed Improvements
17
13 18 17 16 6 11 5 8 2 3 4 10 12 14 9 1 7 19 15 21 20 22 Southbound Northbound San Ysidro/Puerta Mexico
18
Northbound Key Improvements Proposed Expansion of SENTRI Realignment of HOV
19
San Ysidro/Puerta Mexico Northbound Key Improvements SENTRI Lanes Mexico US A
20
Existing Exit Lanes Lane #1Lane #2Lane #3Bus Lane Proposed Exit Lanes Caltrans Share: $300 k CBP Share: $200 k Total Cost: $500 k U.S. SENTRI Exit Lanes Pre Expansion
21
FImprovements to relieve bottleneck at inspection area have been implemented in Mexico FMayor of Tijuana is interested in improving border crossing time into Tijuana San Ysidro/Puerta Mexico Southbound Key Improvements
22
Next Steps FContinue to work with local and federal agencies to complete improvements identified in Bottleneck Study Phase II Other Border Gateways (Unfunded) Phase III U.S./Mexico Border-wide Bottleneck Report (Unfunded)
23
Questions ?
24
Methodology System definition and data collection System capacity analysis Identify bottlenecks and proposed improvements
25
Methodology Data Collection Turn Move Counts Commercial Vehicle Classification Queuing Volumes
26
METHODOLOGY System Capacity Flow Chart
27
Identify Bottlenecks and Proposed Improvements Identify Bottleneck Solution Solution Implementation and Calibration Methodology
28
Methodology Focused on Transportation Outside of the POE Data Collection Schedule Construction Eliminated Pedestrian and Bicycle Data Collection Challenges
29
Successfully developed a methodology to identify low-cost/high result recommendations Conclusions